Building sites that started and stopped in Dublin

648

sites where building started and no completion certificate has followed

  1. Residential Development of 1034 Units at Kilcarbery Grange, Kilcarbery, Dublin 22. Ph 3.12
    Clondalkin · South Dublin · 578 homes · 28 ha · started 25 Aug 2023
  2. Claremont, Residential, Howth -Enabling works
    Howth-Malahide · Fingal · 512 homes · 3.35 ha · started 14 Dec 2020
  3. Residential Development at Hollywoodrath, Hollystown, Dublin 15
    Blanchardstown-Mulhuddart · Fingal · 455 homes · 29 ha · started 24 Jul 2015
  4. Former CIE lands at Carnlough Road, Dublin 7
    Cabra-Glasnevin · Dublin City · 420 homes · started 14 May 2019
  5. Kevin Street (Camden Yard) - Residential Development
    South East Inner City · Dublin City · 299 homes · 1.59 ha · started 9 May 2022
  6. Camden Yard - Piling & Bulk Dig Kevin Street Lower, Dublin 8
    South East Inner City · Dublin City · 299 homes · 1.59 ha · started 23 Feb 2022
  7. Beresford Phase 2 - Comm no. 10
    Rush-Lusk · Fingal · 288 homes · 9.77 ha · started 24 Jun 2022
  8. Greenacres Residential
    Dundrum · Dún Laoghaire-Rathdown · 253 homes · 1.90 ha · started 18 Sept 2019

Checked 25 Sept 2026Data: Buildable · See all 648 →