- 24 Sept 2026 Construction started and not completed
commenced 09 Apr 2018, no completion certificate, planned end May 2018
- 31 Aug 2026 Decision · 6 m
SD26A/0164W: Grant Permission — Removal of the existing revolving entrance door and the construction of a new entrance lobby incorporating automatic dou
- 18 Aug 2026 Commencement notice · 18 m
Work commenced at Lake Drive, Saggart, Dublin, D2400T3
- 8 Jul 2026 New application · 6 m
SD26A/0164W: application received — Removal of the existing revolving entrance door and the construction of a new entrance lobby incorporating automatic dou
- 10 Jun 2026 Commencement notice · 31 m
Work commenced at 3300 Lake Drive, Dublin, D24 TD21 under SD26A/0028W
- 2 Apr 2026 Decision · 19 m
SD26A/0028W: Grant Permission — The development will consist of: The change of use of the existing warehouse to a clean manufacturing area - light indus
- 19 Mar 2026 Decision · 11 m
ED26/0016: Declared Not Exempt — Removal of the existing revolving entrance door and the construction of a new entrance lobby incorporating automatic dou
- 10 Mar 2026 Decision · 107 m
ED26/0012: Declared Not Exempt — Replace an existing 2.4m high Security boundary fence with a 3.0m high fence to secure the GNI Brownsbarn AGI
- 26 Feb 2026 New application · 11 m
ED26/0016: application received — Removal of the existing revolving entrance door and the construction of a new entrance lobby incorporating automatic dou
- 12 Feb 2026 New application · 107 m
ED26/0012: application received — Replace an existing 2.4m high Security boundary fence with a 3.0m high fence to secure the GNI Brownsbarn AGI
- 6 Feb 2026 New application · 19 m
SD26A/0028W: application received — The development will consist of: The change of use of the existing warehouse to a clean manufacturing area - light indus
- 29 Jan 2026 Decision · 18 m
SD25A/0293W: Grant Permission — The development will consist of erection of back-lit signage to the west elevation of Unit 3018.
- 26 Jan 2026 Commencement notice · 56 m
Work commenced at 3008 Lake Drive, Dublin, South Dublin, D24 W283
- 5 Jan 2026 Commencement notice · 62 m
Work commenced at 3030 Lake Drive, Citywest Business Campus, Dublin, South Dublin, xxxx under SD25A/0185W
- 26 Nov 2025 New application · 18 m
SD25A/0293W: application received — The development will consist of erection of back-lit signage to the west elevation of Unit 3018.
- 20 Nov 2025 Decision · 6 m
SD25A/0238W: Grant Permission — The installation of an external Air Handling Unit, to be housed in a new timber and metal clad enclosure adjacent to Uni
- 7 Oct 2025 Decision · 7 m
SD25A/0185W: Grant Permission — The development will consist of alterations to the existing east elevation to include the provision of a new external fi
- 26 Sept 2025 New application · 6 m
SD25A/0238W: application received — The installation of an external Air Handling Unit, to be housed in a new timber and metal clad enclosure adjacent to Uni
- 25 Sept 2025 Decision · 7 m
SD25A/0231W: Invalidate Application — A.) the installation of an external Air Handling Unit, to be housed in a new timber and metal clad enclosure adjacent to
- 23 Sept 2025 Commencement notice · 53 m
Work commenced at 3030 Lake Drive, Citywest Business Campus, Dublin 24, South Dublin, D24 KX6Y under SD25A/0238W
- 19 Sept 2025 New application · 7 m
SD25A/0231W: application received — A.) the installation of an external Air Handling Unit, to be housed in a new timber and metal clad enclosure adjacent to
- 4 Sept 2025 Decision · 63 m
ED25/0066: Declared Exempted and Cannot Determine — Internal sub - division of existing Office building into 4 Office units ( existing office use to be maintained and no ch
- 15 Aug 2025 Commencement notice · 158 m
Work commenced at Riverwalk, Citywest Business Park, Dublin, South Dublin, n/a
- 15 Aug 2025 Further information received · 63 m
ED25/0066: further information received — Internal sub - division of existing Office building into 4 Office units ( existing office use to be maintained and no ch
- 15 Aug 2025 New application · 63 m
ED25/0066: application received — Internal sub - division of existing Office building into 4 Office units ( existing office use to be maintained and no ch
- 14 Aug 2025 Further information requested · 63 m
ED25/0066: further information requested — Internal sub - division of existing Office building into 4 Office units ( existing office use to be maintained and no ch
- 13 Aug 2025 New application · 7 m
SD25A/0185W: application received — The development will consist of alterations to the existing east elevation to include the provision of a new external fi
- 2 May 2025 Commencement notice · 103 m
Work commenced at 4-6 Riverwalk, Citywest Business Campus, Dublin 24, Dublin, South Dublin, D24 DCW0
- 24 Feb 2025 Commencement notice · 116 m
Work commenced at 4 Riverwalk, Dublin, South Dublin, D24 DCW0
- 12 Feb 2025 Decision · 245 m
SD24A/0280W: Grant Permission — The Proposed development will consists of permission of installation of 3no. high level external building signages, one
Events from council registers, the Commission, BCMS, council meetings and the RZLT maps, each with its source link. Open clocks computed with statutory periods (s.34, s.37, s.50 PDA 2000, s.251 Christmas disregard) or as published.