1. Housing Development at BallynerrinNew
Stalled build
Granted with no commencement: 34 homes; commenced 14 May 2018, no completion certificate, planned end Apr 2019 source
34 homes2.71 haWicklow
Stalled build
Granted with no commencement: 34 homes; commenced 14 May 2018, no completion certificate, planned end Apr 2019 source
34 homes2.71 haWicklow
Stalled build
Granted with no commencement: 34 homes; commenced 16 Jul 2018, no completion certificate, planned end Jul 2020 source
34 homes2.20 haWicklow
Stalled build
Granted with no commencement: 59 homes; commenced 08 Sep 2022, no completion certificate, planned end Mar 2023 source
59 homes3.13 haWicklow
Stalled build
Granted with no commencement: 45 homes; commenced 04 Jan 2021, no completion certificate, planned end Sep 2021 source
45 homes2.66 haWicklow
Stalled build
Granted with no commencement: 41 homes; commenced 03 Nov 2022, no completion certificate, planned end Dec 2023 source
41 homes1.34 haWicklow
Stalled build
Granted with no commencement: 15 homes; commenced 08 Jul 2023, no completion certificate, planned end Dec 2023 source
15 homes1.33 haWicklow
Was this site new to you?
Stalled build
Granted with no commencement: 34 homes; commenced 14 Aug 2018, no completion certificate, planned end Aug 2019 source
34 homes2.71 haWicklow
Stalled build
Granted with no commencement: 108 homes; commenced 25 May 2021, no completion certificate, planned end May 2022 source
108 homesCarlow
Stalled build
Granted with no commencement: 106 homes; commenced 27 Sep 2023, no completion certificate, planned end Sep 2024 source
106 homes4.25 haCarlow
Stalled build
Granted with no commencement: 49 homes; commenced 28 Jul 2023, no completion certificate, planned end Mar 2025 source
49 homes1.33 haCarlow
Stalled build
Granted with no commencement: 33 homes; commenced 08 Aug 2023, no completion certificate, planned end Feb 2024 source
33 homes1.55 haKilkenny
Stalled build
Granted with no commencement: 10 homes; commenced 08 Apr 2020, no completion certificate, planned end Dec 2020 source
10 homes0.80 haWestmeath
36 homes1.03 haWestmeath
39 homesWicklow
Stalled build
Granted with no commencement: 62 homes; commenced 17 Aug 2023, no completion certificate, planned end Nov 2023 source
62 homesCarlow
Stalled build
Granted with no commencement: 77 homes; commenced 18 Oct 2022, no completion certificate, planned end Oct 2023 source
77 homesKilkenny
Stalled build
Granted with no commencement: 10 homes; commenced 27 Mar 2023, no completion certificate, planned end Mar 2024 source
10 homes0.53 haWicklow
Was this site new to you?
Stalled build
Granted with no commencement: 30 homes; commenced 16 Jan 2019, no completion certificate, planned end Jan 2020 source
30 homes0.59 haKilkenny
Was this site new to you?
Stalled build
Granted with no commencement: 15 homes; commenced 12 Nov 2018, no completion certificate, planned end Sep 2020 source
15 homes0.27 haKilkenny
Stalled build
Granted with no commencement: 426 homes; commenced 01 Dec 2021, no completion certificate, planned end Nov 2022 source
426 homesWestmeath
Was this site new to you?
Stalled build
Granted with no commencement: 12 homes; commenced 17 Apr 2023, no completion certificate, planned end Oct 2024 source
12 homes0.39 haWestmeath
Stalled build
Granted with no commencement: 13 homes; commenced 15 Nov 2021, no completion certificate, planned end Aug 2022 source
13 homes0.31 haWestmeath
Stalled build
Granted with no commencement: 15 homes; commenced 18 Feb 2015, no completion certificate, planned end Feb 2020 source
15 homesWicklow
Stalled build
Granted with no commencement: 20 homes; commenced 08 Mar 2021, no completion certificate, planned end Dec 2021 source
20 homesWicklow
Stalled build
Granted with no commencement: 16 homes; commenced 05 Feb 2018, no completion certificate, planned end Mar 2019 source
16 homesCarlow