Where are the stalled building sites in Artane-Whitehall?

11 building sites in Artane-Whitehall started work but have no completion certificate, 106 homes in all, as of 25 Sep 2026. Each has a commencement notice with the National Building Control Office and is past its planned finish date.

From public registers, checked 25 Sep 2026. Updated nightly.

Stalled builds in Artane-Whitehall, largest first

  1. 7DN - Beaumont Apartments Block A

    Artane-Whitehall · Dublin City · 0.57 ha · source

    Stalled build

    105 homes; commenced 05 Dec 2022, no completion certificate, planned end Sep 2023

  2. 5 Lorcan Road

    Artane-Whitehall · Dublin City · source

    Stalled build

    1 homes; commenced 30 Jan 2019, no completion certificate, planned end Mar 2019

  3. BT Clonshaugh

    Artane-Whitehall · Dublin City · source

    Stalled build

    commenced 15 Feb 2022, no completion certificate, planned end Mar 2022

  4. 4 Newtown Park, Malahide Road

    Artane-Whitehall · Dublin City · 1.06 ha · source

    Stalled build

    commenced 12 Jun 2023, no completion certificate, planned end Oct 2023

  5. Land in Artane-Whitehall

    Artane-Whitehall · Dublin City · 3.07 ha · source

    Stalled build

    commenced 06 Feb 2020, no completion certificate, planned end Mar 2020

  6. 17 Newtown Road

    Artane-Whitehall · Dublin City · 1.56 ha · source

    Stalled build

    commenced 17 Aug 2023, no completion certificate, planned end Feb 2024

  7. DUB 50 Ventilation Equipment Amendments

    Artane-Whitehall · Dublin City · 3.41 ha · source

    Stalled build

    commenced 30 Jul 2021, no completion certificate, planned end Feb 2022

  8. DUB12 Data Centre, Clonshaugh, Dublin 17 - Fit Out works

    Artane-Whitehall · Dublin City · source

    Stalled build

    commenced 30 Oct 2020, no completion certificate, planned end Jun 2021

  9. Greencastle Rd, Former Tayto Site, Coolock

    Artane-Whitehall · Dublin City · source

    Stalled build

    0 homes; commenced 11 Mar 2019, no completion certificate, planned end Mar 2020

  10. Unit 9A Butterfly Business Park, Artane, Dublin 5

    Artane-Whitehall · Dublin City · source

    Stalled build

    commenced 24 Oct 2018, no completion certificate, planned end Nov 2018

  11. Unit 2, 5 Clonshaugh Road, Dublin 17, D17 TY3

    Artane-Whitehall · Dublin City · source

    Stalled build

    commenced 18 Jun 2018, no completion certificate, planned end Jul 2018

Go further

New development sites in Dublin City, every Monday

The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.

More about Artane-Whitehall

Is there development land for sale in Artane-Whitehall?
Buildable found 23 sites in Artane-Whitehall with a public sign they could come to market, as of 25 Sep 2026: 6 council sites proposed for sale, 3 sites with planning permission running out or recently expired, 3 derelict sites on the register and 11 stalled builds. These come from public registers, not agents' listings, so many are not advertised yet.
How many development sites are there in Artane-Whitehall?
Buildable tracks 481 development sites in Artane-Whitehall, as of 25 Sep 2026: every site with a public reason it could be built on or sold, from the councils' and national registers. They include 6 permitted schemes not started, 4 derelict sites, 7 council land sales and 11 stalled builds.
What are the largest development sites in Artane-Whitehall?
207 development sites in Artane-Whitehall are a hectare or larger, as of 25 Sep 2026. The largest is public land in Artane-Whitehall, at 28.1 ha (publicly owned land).
Where are the derelict sites in Artane-Whitehall?
Artane-Whitehall has 3 sites on the council's derelict sites register, as of 25 Sep 2026. The owner of a registered site pays a levy of 7% of its market value a year.

Data as of 25 Sep 2026. Sources: Commencement and completion notices (National Building Control Office).

Cite this: Where are the stalled building sites in Artane-Whitehall? Buildable, data as of 25 Sep 2026. https://buildable.ie/q/stalled-building-sites-artane-whitehall

Facts from public registers, not advice. Every question · How it works