Where are the stalled building sites in Blanchardstown-Mulhuddart?
26 building sites in Blanchardstown-Mulhuddart started work but have no completion certificate, 468 homes in all, as of 26 Sep 2026. Each has a commencement notice with the National Building Control Office and is past its planned finish date.
From public registers, checked 26 Sep 2026. Updated nightly.
Stalled builds in Blanchardstown-Mulhuddart, largest first
Hollywoodrath, Hollystown, Dublin 15
Blanchardstown-Mulhuddart · Fingal · 28.54 ha · source
Stalled build
455 homes; commenced 24 Jul 2015, no completion certificate, planned end Jul 2016
Northwood Additional Floors
Blanchardstown-Mulhuddart · Fingal · 0.39 ha · source
Stalled build
12 homes; commenced 12 Mar 2020, no completion certificate, planned end Jun 2021
Mosque, Warrenstown House, Dublin 15
Blanchardstown-Mulhuddart · Fingal · 0.78 ha · source
Stalled build
1 homes; commenced 28 Jan 2022, no completion certificate, planned end Jan 2023
ESBN Depot Finglas HVAC replacement
Blanchardstown-Mulhuddart · Fingal · source
Stalled build
commenced 09 Oct 2020, no completion certificate, planned end Nov 2021
ICU Department, Level 3, Connolly Hospital
Blanchardstown-Mulhuddart · Fingal · 20.32 ha · source
Stalled build
commenced 15 Nov 2020, no completion certificate, planned end Nov 2020
Saint Margaret's Park, Dublin 11, Fingal
Blanchardstown-Mulhuddart · Fingal · 4.88 ha · source
Stalled build
commenced 08 Mar 2021, no completion certificate, planned end Jul 2022
K+N Unit D8 - Tenant Fitout
Blanchardstown-Mulhuddart · Fingal · 3.39 ha · source
Stalled build
commenced 04 Jan 2022, no completion certificate, planned end Apr 2022
Synopsys Tenant Fit out - 4th & Part 5th Floors.
Blanchardstown-Mulhuddart · Fingal · 1.34 ha · source
Stalled build
commenced 14 Aug 2023, no completion certificate, planned end Nov 2023
IBM Building 5 minor internal layout modifications
Blanchardstown-Mulhuddart · Fingal · source
Stalled build
commenced 11 Jun 2021, no completion certificate, planned end Aug 2021
DUB 52 Ventilation Equipment Amendments
Blanchardstown-Mulhuddart · Fingal · source
Stalled build
commenced 09 Jul 2021, no completion certificate, planned end Jan 2022
DUB110 Restructure Project
Blanchardstown-Mulhuddart · Fingal · 0.91 ha · source
Stalled build
commenced 16 Jun 2022, no completion certificate, planned end Oct 2022
Industrial Units
Blanchardstown-Mulhuddart · Fingal · 1.2 ha · source
Stalled build
commenced 10 Feb 2023, no completion certificate, planned end May 2023
Farmhand, Damastown
Blanchardstown-Mulhuddart · Fingal · 2.74 ha · source
Stalled build
commenced 06 Dec 2019, no completion certificate, planned end Mar 2020
Car Vacuum Building
Blanchardstown-Mulhuddart · Fingal · 0.96 ha · source
Stalled build
commenced 05 Aug 2020, no completion certificate, planned end Sep 2020
44008 - HSE - National Ambulance Service Facility, North Park, Finglas
Blanchardstown-Mulhuddart · Fingal · source
Stalled build
commenced 15 Feb 2021, no completion certificate, planned end Mar 2021
Unit 35 Rosemount Business Park, Ballycoolin.
Blanchardstown-Mulhuddart · Fingal · source
Stalled build
commenced 02 Jun 2021, no completion certificate, planned end Aug 2021
Saint Margaret's Road, Dublin 11, Fingal
Blanchardstown-Mulhuddart · Fingal · 4.88 ha · source
Stalled build
commenced 01 Feb 2021, no completion certificate, planned end Jun 2022
Bluesteel Kilshane Cross
Blanchardstown-Mulhuddart · Fingal · 0.49 ha · source
Stalled build
commenced 28 Feb 2020, no completion certificate, planned end May 2020
Saint Margaret's Road, Dublin 11, Fingal
Blanchardstown-Mulhuddart · Fingal · 4.88 ha · source
Stalled build
commenced 06 Apr 2021, no completion certificate, planned end Jul 2022
Construct 2 storey commercial unit at Damastown Business Park
Blanchardstown-Mulhuddart · Fingal · 1.06 ha · source
Stalled build
commenced 20 Jul 2022, no completion certificate, planned end Jul 2023
DBS - Proposed Server Areas
Blanchardstown-Mulhuddart · Fingal · 2.71 ha · source
Stalled build
commenced 04 Jan 2019, no completion certificate, planned end Mar 2019
Marcellus Project
Blanchardstown-Mulhuddart · Fingal · 0.87 ha · source
Stalled build
commenced 25 Jan 2023, no completion certificate, planned end Sep 2023
Carwash Building
Blanchardstown-Mulhuddart · Fingal · 1 ha · source
Stalled build
commenced 23 Jul 2020, no completion certificate, planned end Sep 2020
Saint Margaret's Road, Harristown, Swords, Co Dublin, Dublin
Blanchardstown-Mulhuddart · Fingal · 3.67 ha · source
Stalled build
commenced 24 Feb 2020, no completion certificate, planned end May 2020
Yourway, DALP
Blanchardstown-Mulhuddart · Fingal · 2.37 ha · source
Stalled build
commenced 03 Nov 2022, no completion certificate, planned end Dec 2022
Showing 25 of 26. See them all →
Go further
New development sites in Fingal, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
More about Blanchardstown-Mulhuddart
- Is there development land for sale in Blanchardstown-Mulhuddart?
- Buildable found 38 sites in Blanchardstown-Mulhuddart with a public sign they could come to market, as of 26 Sep 2026: 19 council sites proposed for sale, 1 site with planning permission running out or recently expired, 1 derelict site on the register and 26 stalled builds. These come from public registers, not agents' listings, so many are not advertised yet.
- How many development sites are there in Blanchardstown-Mulhuddart?
- Buildable tracks 689 development sites in Blanchardstown-Mulhuddart, as of 26 Sep 2026: every site with a public reason it could be built on or sold, from the councils' and national registers. They include 12 derelict sites, 23 council land sales and 26 stalled builds.
- What are the largest development sites in Blanchardstown-Mulhuddart?
- 198 development sites in Blanchardstown-Mulhuddart are a hectare or larger, as of 26 Sep 2026. The largest is public land in Blanchardstown-Mulhuddart, at 38.9 ha (publicly owned land).
- How much land in Blanchardstown-Mulhuddart is on the RZLT map?
- 299 ha of land in Blanchardstown-Mulhuddart is on the Residential Zoned Land Tax map, across 393 parcels (2027 draft RZLT map), as of 26 Sep 2026. 281 ha of it has no live permission for 10 or more homes. The tax is 3% of market value a year, collected by Revenue on maps the councils make.
Data as of 26 Sep 2026. Sources: Commencement and completion notices (National Building Control Office).
Cite this: Where are the stalled building sites in Blanchardstown-Mulhuddart? Buildable, data as of 26 Sep 2026. https://buildable.ie/q/stalled-building-sites-blanchardstown-mulhuddart
Facts from public registers, not advice. Every question · How it works