Where are the stalled building sites in Dún Laoghaire-Rathdown?
135 building sites in Dún Laoghaire-Rathdown started work but have no completion certificate, 1,827 homes in all, as of 25 Sep 2026. Each has a commencement notice with the National Building Control Office and is past its planned finish date.
From public registers, checked 25 Sep 2026. Updated nightly.
Stalled builds in Dún Laoghaire-Rathdown, largest first
Greenacres Residential
Dundrum · Dún Laoghaire-Rathdown · 1.9 ha · source
Stalled build
253 homes; commenced 18 Sep 2019, no completion certificate, planned end Dec 2019
Beechpark
Killiney-Shankill · Dún Laoghaire-Rathdown · 5.2 ha · source
Stalled build
226 homes; commenced 11 Mar 2019, no completion certificate, planned end Jul 2019
Block B8 - Honeypark
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.04 ha · source
Stalled build
197 homes; commenced 11 Aug 2015, no completion certificate, planned end Aug 2016
Knockrabo Phase 2B - Enabling works
Stillorgan · Dún Laoghaire-Rathdown · 2.75 ha · source
Stalled build
93 homes; commenced 14 Nov 2019, no completion certificate, planned end Feb 2020
Whinsfield Development
Glencullen-Sandyford · Dún Laoghaire-Rathdown · 1.67 ha · source
Stalled build
65 homes; commenced 04 Sep 2020, no completion certificate, planned end Jun 2021
Domville Cherrywood, piling foundation works.
Killiney-Shankill · Dún Laoghaire-Rathdown · 8.39 ha · source
Stalled build
60 homes; commenced 22 Oct 2021, no completion certificate, planned end Oct 2022
Kilmacud House
Stillorgan · Dún Laoghaire-Rathdown · 0.61 ha · source
Stalled build
55 homes; commenced 11 Jun 2018, no completion certificate, planned end Jun 2020
27A Johnstown Road, Cabinteely, Dún Laoghaire-Rathdown
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.31 ha · source
Stalled build
50 homes; commenced 03 Nov 2020, no completion certificate, planned end Oct 2021
27A Johnstown Road, Cabinteely, Dún Laoghaire-Rathdown
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.31 ha · source
Stalled build
50 homes; commenced 06 Apr 2021, no completion certificate, planned end Mar 2022
27A Johnstown Road, Cabinteely
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.31 ha · source
Stalled build
50 homes; commenced 18 Feb 2020, no completion certificate, planned end Jun 2020
Prague, Johnstown Road, Dun Laoghaire
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.29 ha · source
Stalled build
49 homes; commenced 02 Aug 2019, no completion certificate, planned end Sep 2020
21 Johnstown Road, Cabinteely
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.29 ha · source
Stalled build
49 homes; commenced 14 Jun 2019, no completion certificate, planned end Sep 2019
Deerpark Road, Mount Merrion, Blackrock
Stillorgan · Dún Laoghaire-Rathdown · 0.34 ha · source
Stalled build
48 homes; commenced 16 Aug 2019, no completion certificate, planned end May 2021
Stillorgan Gate
Stillorgan · Dún Laoghaire-Rathdown · 0.86 ha · source
Stalled build
48 homes; commenced 04 Aug 2015, no completion certificate, planned end Aug 2017
Glenamuck Road, Carrickmines, Dublin 18
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.47 ha · source
Stalled build
48 homes; commenced 18 Jan 2021, no completion certificate, planned end Dec 2022
Church Road, Killiney
Killiney-Shankill · Dún Laoghaire-Rathdown · 1.19 ha · source
Stalled build
47 homes; commenced 06 Aug 2019, no completion certificate, planned end Nov 2019
Drummartin Apartments
Stillorgan · Dún Laoghaire-Rathdown · 0.29 ha · source
Stalled build
47 homes; commenced 23 Sep 2022, no completion certificate, planned end Aug 2024
Belmont, Stepaside, Co. Dublin
Glencullen-Sandyford · Dún Laoghaire-Rathdown · 1.38 ha · source
Stalled build
37 homes; commenced 16 Jun 2014, no completion certificate, planned end Jan 2015
HERONS WOOD
Stillorgan · Dún Laoghaire-Rathdown · 0.57 ha · source
Stalled build
34 homes; commenced 04 May 2021, no completion certificate, planned end Sep 2022
Herons Wood
Stillorgan · Dún Laoghaire-Rathdown · 0.57 ha · source
Stalled build
34 homes; commenced 18 Jul 2022, no completion certificate, planned end Feb 2024
Monkstown Grove Residential Development
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.22 ha · source
Stalled build
30 homes; commenced 03 Feb 2022, no completion certificate, planned end Mar 2022
Dun Oir Residential Phase 4
Glencullen-Sandyford · Dún Laoghaire-Rathdown · 4.5 ha · source
Stalled build
27 homes; commenced 03 Nov 2022, no completion certificate, planned end Aug 2023
39 Castle Park Road, Dalkey
Dún Laoghaire · Dún Laoghaire-Rathdown · 0.46 ha · source
Stalled build
24 homes; commenced 25 Apr 2022, no completion certificate, planned end Aug 2022
Sringfield House, Springfield Park, Foxrock
Stillorgan · Dún Laoghaire-Rathdown · 0.68 ha · source
Stalled build
23 homes; commenced 01 Mar 2018, no completion certificate, planned end Jun 2018
Eaton Brae Shankill Phase 1
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.61 ha · source
Stalled build
16 homes; commenced 18 Oct 2018, no completion certificate, planned end Aug 2019
Showing 25 of 135. See them all →
Go further
New development sites in Dún Laoghaire-Rathdown, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
More about Dún Laoghaire-Rathdown
- Is there development land for sale in Dún Laoghaire-Rathdown?
- Buildable found 165 sites in Dún Laoghaire-Rathdown with a public sign they could come to market, as of 25 Sep 2026: 2 council sites proposed for sale, 12 sites with planning permission running out or recently expired, 16 derelict sites on the register and 135 stalled builds. These come from public registers, not agents' listings, so many are not advertised yet.
- How many development sites are there in Dún Laoghaire-Rathdown?
- Buildable tracks 2,732 development sites in Dún Laoghaire-Rathdown, as of 25 Sep 2026: every site with a public reason it could be built on or sold, from the councils' and national registers. They include 8 permissions running out, 41 permitted schemes not started, 20 derelict sites, 2 council land sales and 135 stalled builds.
- What are the largest development sites in Dún Laoghaire-Rathdown?
- 1,074 development sites in Dún Laoghaire-Rathdown are a hectare or larger, as of 25 Sep 2026. The largest is public land in Glencullen-Sandyford, at 70.1 ha (publicly owned land).
- Where are the derelict sites in Dún Laoghaire-Rathdown?
- Dún Laoghaire-Rathdown has 16 sites on the council's derelict sites register, as of 25 Sep 2026. The owner of a registered site pays a levy of 7% of its market value a year.
Data as of 25 Sep 2026. Sources: Commencement and completion notices (National Building Control Office).