Where are the stalled building sites in Dundrum?
10 building sites in Dundrum started work but have no completion certificate, 287 homes in all, as of 25 Sep 2026. Each has a commencement notice with the National Building Control Office and is past its planned finish date.
From public registers, checked 25 Sep 2026. Updated nightly.
Stalled builds in Dundrum, largest first
Greenacres Residential
Dundrum · Dún Laoghaire-Rathdown · 1.9 ha · source
Stalled build
253 homes; commenced 18 Sep 2019, no completion certificate, planned end Dec 2019
Embassy of the Russian Federation in Ireland
Dundrum · Dún Laoghaire-Rathdown · 2.18 ha · source
Stalled build
16 homes; commenced 25 Nov 2019, no completion certificate, planned end Nov 2020
Embassy of the Russian Federation in Ireland
Dundrum · Dún Laoghaire-Rathdown · 2.18 ha · source
Stalled build
16 homes; commenced 15 Jul 2019, no completion certificate, planned end May 2020
100 Marlay Court, Dublin
Dundrum · Dún Laoghaire-Rathdown · 0.03 ha · source
Stalled build
1 homes; commenced 22 Jun 2020, no completion certificate, planned end Sep 2020
Thorncliffe
Dundrum · Dún Laoghaire-Rathdown · 0.05 ha · source
Stalled build
1 homes; commenced 25 Aug 2022, no completion certificate, planned end Nov 2022
BT Dundrum
Dundrum · Dún Laoghaire-Rathdown · source
Stalled build
commenced 15 Feb 2022, no completion certificate, planned end May 2022
RSA - Fit-out
Dundrum · Dún Laoghaire-Rathdown · 3.12 ha · source
Stalled build
commenced 02 Dec 2021, no completion certificate, planned end Feb 2022
The Grove Student Accommodation Block N
Dundrum · Dún Laoghaire-Rathdown · 2.14 ha · source
Stalled build
commenced 28 Mar 2022, no completion certificate, planned end Sep 2023
Sandyford Road, Dundrum Town Centre, Dún Laoghaire-Rathdown
Dundrum · Dún Laoghaire-Rathdown · 0.49 ha · source
Stalled build
commenced 20 Dec 2022, no completion certificate, planned end Dec 2022
RSA House, Sandyford Road, Dundrum
Dundrum · Dún Laoghaire-Rathdown · 0.06 ha · source
Stalled build
commenced 18 May 2021, no completion certificate, planned end Jul 2021
Go further
New development sites in Dún Laoghaire-Rathdown, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
More about Dundrum
- Is there development land for sale in Dundrum?
- Buildable found 13 sites in Dundrum with a public sign they could come to market, as of 25 Sep 2026: 2 sites with planning permission running out or recently expired, 1 derelict site on the register and 10 stalled builds. These come from public registers, not agents' listings, so many are not advertised yet.
- How many development sites are there in Dundrum?
- Buildable tracks 421 development sites in Dundrum, as of 25 Sep 2026: every site with a public reason it could be built on or sold, from the councils' and national registers. They include 2 permissions running out, 4 permitted schemes not started, 1 derelict site and 10 stalled builds.
- What are the largest development sites in Dundrum?
- 192 development sites in Dundrum are a hectare or larger, as of 25 Sep 2026. The largest is land in Dundrum, at 24.7 ha (on the rzlt map, no permission).
- How much land in Dundrum is on the RZLT map?
- 520 ha of land in Dundrum is on the Residential Zoned Land Tax map, across 335 parcels (2027 draft RZLT map), as of 25 Sep 2026. 472 ha of it has no live permission for 10 or more homes. The tax is 3% of market value a year, collected by Revenue on maps the councils make.
Data as of 25 Sep 2026. Sources: Commencement and completion notices (National Building Control Office).
Cite this: Where are the stalled building sites in Dundrum? Buildable, data as of 25 Sep 2026. https://buildable.ie/q/stalled-building-sites-dundrum