Where are the stalled building sites in Killiney-Shankill?
27 building sites in Killiney-Shankill started work but have no completion certificate, 421 homes in all, as of 25 Sep 2026. Each has a commencement notice with the National Building Control Office and is past its planned finish date.
From public registers, checked 25 Sep 2026. Updated nightly.
Stalled builds in Killiney-Shankill, largest first
Beechpark
Killiney-Shankill · Dún Laoghaire-Rathdown · 5.2 ha · source
Stalled build
226 homes; commenced 11 Mar 2019, no completion certificate, planned end Jul 2019
Domville Cherrywood, piling foundation works.
Killiney-Shankill · Dún Laoghaire-Rathdown · 8.39 ha · source
Stalled build
60 homes; commenced 22 Oct 2021, no completion certificate, planned end Oct 2022
Glenamuck Road, Carrickmines, Dublin 18
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.47 ha · source
Stalled build
48 homes; commenced 18 Jan 2021, no completion certificate, planned end Dec 2022
Church Road, Killiney
Killiney-Shankill · Dún Laoghaire-Rathdown · 1.19 ha · source
Stalled build
47 homes; commenced 06 Aug 2019, no completion certificate, planned end Nov 2019
Eaton Brae Shankill Phase 1
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.61 ha · source
Stalled build
16 homes; commenced 18 Oct 2018, no completion certificate, planned end Aug 2019
No. 2 Cluny Manor, Avondale Road, Killiney
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.68 ha · source
Stalled build
10 homes; commenced 23 Apr 2015, no completion certificate, planned end Dec 2015
No. 4 Cluny Manor, Avondale Road, Killiney
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.68 ha · source
Stalled build
10 homes; commenced 23 Apr 2015, no completion certificate, planned end Jan 2016
TC 1 Soil Excavation
Killiney-Shankill · Dún Laoghaire-Rathdown · 16.99 ha · source
Stalled build
1 homes; commenced 20 May 2020, no completion certificate, planned end Aug 2020
Cherrywood TC 1 Site Works
Killiney-Shankill · Dún Laoghaire-Rathdown · 16.99 ha · source
Stalled build
1 homes; commenced 08 Feb 2021, no completion certificate, planned end Jun 2021
Cherrywood L1 and L2 Enabling Works
Killiney-Shankill · Dún Laoghaire-Rathdown · 9.79 ha · source
Stalled build
1 homes; commenced 14 Feb 2022, no completion certificate, planned end Jun 2022
Cherrywood Town Centre 4 Residential
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.03 ha · source
Stalled build
1 homes; commenced 12 Nov 2018, no completion certificate, planned end Jan 2019
T8 Cherrywood Enabling Works, Cherrywood, Dublin 18
Killiney-Shankill · Dún Laoghaire-Rathdown · 9.79 ha · source
Stalled build
commenced 21 May 2021, no completion certificate, planned end Sep 2021
Friends First House
Killiney-Shankill · Dún Laoghaire-Rathdown · 25.65 ha · source
Stalled build
commenced 12 May 2021, no completion certificate, planned end Aug 2021
T6 Cherrywood Enabling Works, Cherrywood, Dublin 18
Killiney-Shankill · Dún Laoghaire-Rathdown · 9.79 ha · source
Stalled build
commenced 21 May 2021, no completion certificate, planned end Sep 2021
Cherrywood Town Centre 4 Site Clearance
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.04 ha · source
Stalled build
0 homes; commenced 12 Nov 2018, no completion certificate, planned end Jan 2019
Cherrywood TC2 Enabling Works
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.03 ha · source
Stalled build
commenced 19 Dec 2018, no completion certificate, planned end Feb 2019
Cherrywood Business Park, Building 4, Dublin
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.46 ha · source
Stalled build
commenced 26 Feb 2019, no completion certificate, planned end Apr 2019
Cherrywood Block F3
Killiney-Shankill · Dún Laoghaire-Rathdown · 2.58 ha · source
Stalled build
commenced 15 Jul 2019, no completion certificate, planned end Aug 2019
Campus upgrade works to Cherrywood Business Park
Killiney-Shankill · Dún Laoghaire-Rathdown · 4.28 ha · source
Stalled build
commenced 26 Mar 2020, no completion certificate, planned end Jan 2021
T2 Cherrywood Enabling Works, Cherrywood, Dublin 18
Killiney-Shankill · Dún Laoghaire-Rathdown · 9.68 ha · source
Stalled build
commenced 14 Apr 2021, no completion certificate, planned end Oct 2021
Refurbishment of Block 3 and Block 4, Cherrywood Business Park.
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.65 ha · source
Stalled build
commenced 16 Jan 2019, no completion certificate, planned end Mar 2019
Building 10 Cherrywood Business Park
Killiney-Shankill · Dún Laoghaire-Rathdown · 1.46 ha · source
Stalled build
commenced 17 Jun 2019, no completion certificate, planned end Sep 2019
Accenture Cherrywood Phase 3
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.43 ha · source
Stalled build
commenced 26 Aug 2021, no completion certificate, planned end Dec 2021
APC Labs Cherrywood Phase 5
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.5 ha · source
Stalled build
commenced 02 Dec 2020, no completion certificate, planned end May 2021
Cherrywood, Ground Floor Fit-out
Killiney-Shankill · Dún Laoghaire-Rathdown · 0.5 ha · source
Stalled build
commenced 18 Mar 2019, no completion certificate, planned end Jun 2019
Showing 25 of 27. See them all →
Go further
New development sites in Dún Laoghaire-Rathdown, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
More about Killiney-Shankill
- Is there development land for sale in Killiney-Shankill?
- Buildable found 29 sites in Killiney-Shankill with a public sign they could come to market, as of 25 Sep 2026: 2 derelict sites on the register and 27 stalled builds. These come from public registers, not agents' listings, so many are not advertised yet.
- How many development sites are there in Killiney-Shankill?
- Buildable tracks 633 development sites in Killiney-Shankill, as of 25 Sep 2026: every site with a public reason it could be built on or sold, from the councils' and national registers. They include 9 permitted schemes not started, 2 derelict sites and 27 stalled builds.
- What are the largest development sites in Killiney-Shankill?
- 218 development sites in Killiney-Shankill are a hectare or larger, as of 25 Sep 2026. The largest is land in Killiney-Shankill, at 36.1 ha (on the rzlt map, no permission).
- How much land in Killiney-Shankill is on the RZLT map?
- 668 ha of land in Killiney-Shankill is on the Residential Zoned Land Tax map, across 448 parcels (2027 draft RZLT map), as of 25 Sep 2026. 519 ha of it has no live permission for 10 or more homes. The tax is 3% of market value a year, collected by Revenue on maps the councils make.
Data as of 25 Sep 2026. Sources: Commencement and completion notices (National Building Control Office).