- 24 Sept 2026 Public land (LDA register)
Held by Córas Iompair Éireann
- 24 Sept 2026 Built far below what the zoning allows
No buildings on 0.14 ha
- 27 Aug 2026 Decision · 12 m
FW26A/0017E: GRANT TIME EXT (3 months) AI — The Electricity Supply Board (ESB) intends to apply for permission for
- 26 Aug 2026 Commencement notice · 242 m
Work commenced at 2 Barberstown Lane North, Dublin 15, Dublin under FW25A/0373E (1 dwelling unit)
- 31 Jul 2026 Appeal received by the Commission · 167 m
ACP 324526: RZLT inclusion on final Residential Zoned land tax map
- 31 Jul 2026 Appeal received by the Commission · 84 m
ACP 324524: RZLT inclusion on final Residential Zoned land tax map
- 31 Jul 2026 Appeal received by the Commission · 19 m
ACP 324511: RZLT inclusion on final Residential Zoned land tax map
- 6 Jul 2026 Commencement notice · 244 m
Work commenced at No. 02 Barberstown Lane N, Dublin 15, Dublin, D15 V08R under FW25A/0373E (1 dwelling unit)
- 26 May 2026 Decision · 230 m
FW25A/0361E: App withdrawn as no AI recd in 6 months — Construction of a new 1 storey / 2 storey extension to side / rear, wi
- 26 May 2026 Decision · 228 m
FW26A/0133E: GRANT PERMISSION — The development will consist of converting the attic, the construction
- 28 Apr 2026 Decision · 229 m
FW25A/0373E: GRANT PERMISSION — Construction of a new 1 storey / 2 storey extension to side / rear, wi
- 16 Apr 2026 Decision · 115 m
FW25A/0548E: GRANT PERMISSION — The development will consist of modifications to the development permi
- 2 Apr 2026 Further information received · 229 m
FW25A/0373E: further information received — Construction of a new 1 storey / 2 storey extension to side / rear, wi
- 2 Apr 2026 New application · 228 m
FW26A/0133E: application received — The development will consist of converting the attic, the construction
- 31 Mar 2026 Decision · 228 m
FW26A/0127E: Invalid Application — The development will consist of the construction of a dormer window in
- 30 Mar 2026 New application · 228 m
FW26A/0127E: application received — The development will consist of the construction of a dormer window in
- 24 Mar 2026 Further information received · 115 m
FW25A/0548E: further information received — The development will consist of modifications to the development permi
- 19 Mar 2026 Further information requested · 115 m
FW25A/0548E: further information requested — The development will consist of modifications to the development permi
- 16 Mar 2026 Commencement notice · 199 m
Work commenced at CLONSILLA ROAD, CLONSILLA, Fingal, D15 T2FW
- 12 Mar 2026 Further information requested · 12 m
FW26A/0017E: further information requested — The Electricity Supply Board (ESB) intends to apply for permission for
- 5 Mar 2026 Decision · 228 m
FW26A/0013E: REFUSE PERMISSION — The development will consist of the construction of a dormer window in
- 10 Feb 2026 Sale recorded (PPR) · 226 m
€540,000 · 6 PARK VIEW, HANSFIELD WOOD, HANSFIELD · second-hand
- 10 Feb 2026 Further information requested · 229 m
FW25A/0373E: further information requested — Construction of a new 1 storey / 2 storey extension to side / rear, wi
- 16 Jan 2026 Decision · 12 m
FW26A/0017E: REQUEST ADDITIONAL INFORMATION — The Electricity Supply Board (ESB) intends to apply for permission for
- 16 Jan 2026 New application · 12 m
FW26A/0017E: application received — The Electricity Supply Board (ESB) intends to apply for permission for
- 15 Jan 2026 New application · 228 m
FW26A/0013E: application received — The development will consist of the construction of a dormer window in
- 13 Jan 2026 Decision · 228 m
FW26A/0008E: Invalid Application — The development will consist of the construction of a dormer window in
- 12 Jan 2026 New application · 228 m
FW26A/0008E: application received — The development will consist of the construction of a dormer window in
- 17 Dec 2025 New application · 115 m
FW25A/0548E: application received — The development will consist of modifications to the development permi
- 12 Dec 2025 Commencement notice · 104 m
Work commenced at 8 Station Road, Dublin, Fingal, D15 KDT2 under FW22A/0020