- 24 Sept 2026 Public land (LDA register)
Held by Fingal County Council
- 19 Sept 2025 Commencement notice · 174 m
Work commenced at Damastown Avenue, Dublin, Fingal under PARTX/001/23
- 19 Sept 2025 Commencement notice · 67 m
Work commenced at Block E Bin Store, Church Fields Phase 2 (3B), Mulhuddart, Dublin, Fingal under PARTX/001/23
- 27 Jun 2025 Commencement notice · 154 m
Work commenced at Block F Bin Store, Church Fields Phase 2 (3B), Mulhuddart, Dublin, Fingal under PARTX/001/23
- 8 May 2025 Commencement notice · 170 m
Work commenced at Block D, Church Fields (Phase 3B), Mulhuddart, Dublin, Fingal under PARTX/001/23 (32 dwelling units)
- 30 Apr 2025 Commencement notice · 120 m
Work commenced at Block E Church Fields, Mulhuddart, Dublin 15, Fingal under PARTX/001/23 (32 dwelling units)
- 27 Jan 2025 Commencement notice · 106 m
Work commenced at Damastown, Dublin, Fingal under PARTX/001/23 (32 dwelling units)
- 4 Dec 2024 Decision · 206 m
FW24A/0250E: GRANT PERMISSION — proposed new signage and LED screen to existing school building
- 8 Nov 2024 Further information received · 206 m
FW24A/0250E: further information received — proposed new signage and LED screen to existing school building
- 2 Oct 2024 Further information requested · 206 m
FW24A/0250E: further information requested — proposed new signage and LED screen to existing school building
- 30 Sept 2024 Commencement notice · 75 m
Work commenced at Damastown Avenue, Mulhuddart, Fingal under PARTX/001/23 (121 dwelling units)
- 13 Jun 2024 New application · 206 m
FW24A/0250E: application received — proposed new signage and LED screen to existing school building
- 17 Nov 2023 Appeal decided · 28 m
ACP 317346: Approve with Conditions
- 7 Jun 2023 Appeal received by the Commission · 28 m
ACP 317346: Proposed development of 217 no. residential units, consisting of 121 no. houses and 96 no. apartments, ranging from 2-4
- 15 Nov 2021 Decision · 237 m
FW21A/0173: GRANT PERMISSION & GRANT RETENTION — Minor amendments to existing planning approvals (FW16A/0181; FW18A/010
- 24 Sept 2021 New application · 237 m
FW21A/0173: application received — Minor amendments to existing planning approvals (FW16A/0181; FW18A/010
- 11 Mar 2021 Decision · 198 m
FW21A/0007: GRANT PERMISSION & GRANT RETENTION — The development consisting of/will consist of the retention and reconf
- 22 Jan 2021 New application · 198 m
FW21A/0007: application received — The development consisting of/will consist of the retention and reconf
- 9 Oct 2020 Appeal decided · 158 m
ACP 306834: Approve with Conditions
- 6 Mar 2020 Appeal received by the Commission · 158 m
ACP 306834: Provision of a double circuit 220kV transmission line and a 220kV gas insulated switchgear (GIS) substation along with a
- 13 Feb 2020 Decision · 225 m
FW19A/0212: GRANT PERMISSION — The development consists of modifications to the development permitted
- 17 Dec 2019 Decision · 202 m
FW19A/0177: GRANT PERMISSION — The Electricity Supply Board (ESB) intends to apply for planning permi
- 11 Dec 2019 New application · 225 m
FW19A/0212: application received — The development consists of modifications to the development permitted
- 29 Oct 2019 New application · 202 m
FW19A/0177: application received — The Electricity Supply Board (ESB) intends to apply for planning permi
- 5 Sept 2019 Decision · 198 m
FW19A/0125: GRANT PERMISSION & GRANT RETENTION — Permission for 2 no. windows located on the north elevation on mezzani
- 31 Jul 2019 Further information requested · 198 m
FW19A/0125: further information requested — Permission for 2 no. windows located on the north elevation on mezzani
- 23 Jul 2019 Decision · 56 m
FW19A/0088: GRANT PERMISSION FOR RETENTION — The development consists of an existing 24 metre high telecommunicatio
- 22 Jul 2019 New application · 198 m
FW19A/0125: application received — Permission for 2 no. windows located on the north elevation on mezzani
- 30 May 2019 New application · 56 m
FW19A/0088: application received — The development consists of an existing 24 metre high telecommunicatio
- 6 Sept 2018 Decision · 225 m
FW18A/0103: GRANT PERMISSION — Construction of a new single storey ESB Substation and all ancillary s
Events from council registers, the Commission, BCMS, council meetings and the RZLT maps, each with its source link. Open clocks computed with statutory periods (s.34, s.37, s.50 PDA 2000, s.251 Christmas disregard) or as published.