1. St Patrick's CourtNew
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 45 days10 homes0.87 haLongford
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 45 days10 homes0.87 haLongford
Derelict siteOn the RZLT map (3% land tax)On the RZLT map, no permission
On the council's derelict sites register: Register ref DS: 1705 source
87–248 homes3.11 haDún Laoghaire-Rathdown
Was this site new to you?
Derelict siteOn the RZLT map (3% land tax)On the RZLT map, no permission
On the council's derelict sites register: Register ref DS: 1696 source
66–189 homes2.37 haDún Laoghaire-Rathdown
Was this site new to you?
Permission running out
45 homes granted 30 Mar 2022, expires 29 Mar 2027, not started source
Expires in 164 days45 homes2.28 haWexford
Was this site new to you?
Expires in 335 days12 homes0.50 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 31 homes; commenced 26 Apr 2018, no completion certificate, planned end Aug 2019 source
31 homes1.55 haLongford
Stalled build
Granted with no commencement: 12 homes; commenced 03 Sep 2018, no completion certificate, planned end Sep 2019 source
12 homes2.09 haLongford
Stalled build
Granted with no commencement: 37 homes; commenced 16 Jun 2014, no completion certificate, planned end Jan 2015 source
37 homes1.39 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 23 homes; commenced 01 Mar 2018, no completion certificate, planned end Jun 2018 source
23 homes0.68 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 16 homes; commenced 18 Oct 2018, no completion certificate, planned end Aug 2019 source
16 homes0.61 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 47 homes; commenced 06 Aug 2019, no completion certificate, planned end Nov 2019 source
47 homes1.19 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 16 homes; commenced 25 Nov 2019, no completion certificate, planned end Nov 2020 source
16 homes2.18 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 34 homes; commenced 04 May 2021, no completion certificate, planned end Sep 2022 source
34 homes0.57 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 34 homes; commenced 18 Jul 2022, no completion certificate, planned end Feb 2024 source
34 homes0.57 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 27 homes; commenced 03 Nov 2022, no completion certificate, planned end Aug 2023 source
27 homes4.50 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 39 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
39 homes3.30 haFingal
Stalled build
Granted with no commencement: 253 homes; commenced 18 Sep 2019, no completion certificate, planned end Dec 2019 source
253 homes1.90 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 55 homes; commenced 30 Mar 2023, no completion certificate, planned end Dec 2023 source
55 homes1.35 haFingal
Stalled build
Granted with no commencement: 10 homes; commenced 23 Apr 2015, no completion certificate, planned end Dec 2015 source
10 homes0.68 haDún Laoghaire-Rathdown
Was this site new to you?
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Sep 2024 source
15 homes2.79 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 198 homes; commenced 23 May 2022, no completion certificate, planned end Dec 2023 source
198 homes0.77 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 08 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Can’t find what you need?