1. St Patrick's CourtNew
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 44 days10 homes0.87 haLongford
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 44 days10 homes0.87 haLongford
Permission running out
26 homes granted 9 Aug 2022, expires 8 Aug 2027, not started source
Expires in 295 days26 homes1.85 haOffaly
Was this site new to you?
Derelict siteOn the RZLT map (3% land tax)On the RZLT map, no permission
On the council's derelict sites register: Register ref 1726, entered 16 Feb 2015, market value €145,000 source
18–51 homes0.65 haSouth Dublin
Permission running out
45 homes granted 30 Mar 2022, expires 29 Mar 2027, not started source
Expires in 163 days45 homes2.28 haWexford
Was this site new to you?
Stalled build
Granted with no commencement: 385 homes; commenced 10 Aug 2021, no completion certificate, planned end Sep 2022 source
385 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 05 Jul 2021, no completion certificate, planned end Feb 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 28 Apr 2021, no completion certificate, planned end Oct 2021 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 14 Oct 2021, no completion certificate, planned end Jul 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 30 Jul 2021, no completion certificate, planned end Jul 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 04 Aug 2021, no completion certificate, planned end Jun 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 108 homes; commenced 25 May 2021, no completion certificate, planned end May 2022 source
108 homesCarlow
Stalled build
Granted with no commencement: 106 homes; commenced 27 Sep 2023, no completion certificate, planned end Sep 2024 source
106 homes4.25 haCarlow
Stalled build
Granted with no commencement: 49 homes; commenced 28 Jul 2023, no completion certificate, planned end Mar 2025 source
49 homes1.33 haCarlow
Stalled build
Granted with no commencement: 31 homes; commenced 26 Apr 2018, no completion certificate, planned end Aug 2019 source
31 homes1.55 haLongford
Stalled build
Granted with no commencement: 12 homes; commenced 03 Sep 2018, no completion certificate, planned end Sep 2019 source
12 homes2.09 haLongford
Stalled build
Granted with no commencement: 10 homes; commenced 08 Apr 2020, no completion certificate, planned end Dec 2020 source
10 homes0.80 haWestmeath
36 homes1.03 haWestmeath
Stalled build
Granted with no commencement: 39 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
39 homes3.30 haFingal
Stalled build
Granted with no commencement: 55 homes; commenced 30 Mar 2023, no completion certificate, planned end Dec 2023 source
55 homes1.35 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Sep 2024 source
15 homes2.79 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 198 homes; commenced 23 May 2022, no completion certificate, planned end Dec 2023 source
198 homes0.77 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 08 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Can’t find what you need?