1. part of former Minch Norton MaltingsNew
Permission running out
19 homes granted 2 Nov 2021, expires 1 Nov 2026, not started source
Expires in 16 days19 homes0.88 haLaois
Permission running out
19 homes granted 2 Nov 2021, expires 1 Nov 2026, not started source
Expires in 16 days19 homes0.88 haLaois
Permission running out
131 homes granted 16 Feb 2022, expires 16 Feb 2027, not started source
Expires in 123 days131 homes2.47 haSouth Dublin
Was this site new to you?
Permission running out
58 homes granted 8 Feb 2022, expires 7 Feb 2027, not started source
Expires in 114 days58 homes1.45 haLaois
Was this site new to you?
Expires in 114 days26 homes1.25 haLaois
20 homes0.70 haOffaly
Expires in 268 days10 homes1.05 haCarlow
Was this site new to you?
Permission running out
26 homes granted 9 Aug 2022, expires 8 Aug 2027, not started source
Expires in 296 days26 homes1.85 haOffaly
Permitted, not started
95 homes granted 24 May 2023, not started; permission runs to 3 Mar 2029 source
95 homes3.06 haOffaly
Was this site new to you?
Permission running out
98 homes granted 23 Jun 2026, expires 22 Mar 2027, not started source
Expires in 157 days98 homes5.71 haOffaly
Was this site new to you?
Derelict siteOn the RZLT map (3% land tax)On the RZLT map, no permission
On the council's derelict sites register: Register ref 1726, entered 16 Feb 2015, market value €145,000 source
18–51 homes0.65 haSouth Dublin
Permission running out
10 homes granted 18 Jan 2022, expires 17 Jan 2027, not started source
Expires in 93 days10 homes0.33 haCarlow
Permission running out
45 homes granted 30 Mar 2022, expires 29 Mar 2027, not started source
Expires in 164 days45 homes2.28 haWexford
Was this site new to you?
Permitted, not started
10 homes granted 13 Jan 2025, not started; permission runs to 12 Jan 2030 source
10 homes0.34 haWestmeath
Expires in 274 days60 homes2.20 haWexford
Was this site new to you?
Stalled build
Granted with no commencement: 58 homes; commenced 20 Aug 2018, no completion certificate, planned end Nov 2018 source
58 homes1.95 haWexford
Stalled build
Granted with no commencement: 108 homes; commenced 25 May 2021, no completion certificate, planned end May 2022 source
108 homesCarlow
Stalled build
Granted with no commencement: 49 homes; commenced 28 Jul 2023, no completion certificate, planned end Mar 2025 source
49 homes1.33 haCarlow
Stalled build
Granted with no commencement: 23 homes; commenced 27 Jun 2023, no completion certificate, planned end Aug 2024 source
23 homes0.85 haLaois
36 homes1.03 haWestmeath
Stalled build
Granted with no commencement: 83 homes; commenced 05 May 2021, no completion certificate, planned end Nov 2021 source
83 homes3.56 haWexford
Stalled build
Granted with no commencement: 114 homes; commenced 11 Jun 2018, no completion certificate, planned end Oct 2018 source
114 homes0.59 haSouth Dublin
Stalled build
Granted with no commencement: 93 homes; commenced 25 Apr 2022, no completion certificate, planned end Apr 2024 source
93 homes2.15 haSouth Dublin
Stalled build
Granted with no commencement: 72 homes; commenced 09 Feb 2015, no completion certificate, planned end May 2015 source
72 homes3.36 haSouth Dublin
Stalled build
Granted with no commencement: 12 homes; commenced 22 Aug 2022, no completion certificate, planned end Aug 2023 source
12 homes3.25 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 16 homes; commenced 04 Jan 2022, no completion certificate, planned end Jan 2024 source
16 homes3.25 haSouth Dublin
Was this site new to you?