Building sites that started and stopped in Laois commenced, not completed

Housing with a commencement notice but no completion certificate, largest first.

13 sites where building started and no completion certificate has followed

13 new this week

  • 1 ha in all
  • 600 homes
  • checked 12 Oct 2026

New this week

  1. Old Knockmay Road, Portlaoise, Co. Laois

    Old Knockmay Road, Portlaoise, Laois · Portlaoise · 33 homes · started 19 Oct 2016 · source

    33 homes; commenced 19 Oct 2016, no completion certificate, planned end Jul 2018

  2. Ashewood Walk, Portlaoise, Laois

    Portlaoise · 20 homes · started 11 Oct 2016 · source

    20 homes; commenced 11 Oct 2016, no completion certificate, planned end Oct 2017

  3. Ashewood Walk, Portlaoise, Laois

    Portlaoise · 20 homes · started 11 Aug 2016 · source

    20 homes; commenced 11 Aug 2016, no completion certificate, planned end Jul 2017

  4. Dunamaise View

    11 Heathfields, Portlaoise, Laois · Portlaoise · 36 homes · started 30 Jan 2020 · source

    36 homes; commenced 30 Jan 2020, no completion certificate, planned end Jan 2021

  5. Cross of Newtown

    73 The Cross of Newtown, Ballyroan, Laois · Portlaoise · 0.85 ha · 23 homes · started 27 Jun 2023 · source

    23 homes; commenced 27 Jun 2023, no completion certificate, planned end Aug 2024

Open all 13 on the map

Stalled builds in Laois, every Monday

The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.

8 more of 13

  1. 85 Lake Drive, Portlaoise, Laois

    Skibbereen-West Cork · 0.02 ha · 150 homes · started 28 Oct 2021 · source

  2. Millers Hill, Killenard, Killenard, Laois

    Skibbereen-West Cork · 0.03 ha · 79 homes · started 18 Aug 2022 · source

  3. Castlelea Avenue

    Unnamed Road, Portarlington, Laois · Graiguecullen-Portarlington · 0.00 ha · 67 homes · started 15 Jun 2021 · source

  4. Castlelea Avenue

    11 Castlelea Avenue, Portarlington, Laois · Skibbereen-West Cork · 0.27 ha · 62 homes · started 21 Jan 2020 · source

  5. Windmill Hill at the Heritage, Killenard, Co Laois

    15 Mount Henry Drive, Killenard, Laois, R32 CK03 · Graiguecullen-Portarlington · 43 homes · started 30 Apr 2019 · source

  6. DUNAMAISE VIEW - Phase 2

    11 Heathfields, Portlaoise, Laois · Portlaoise · 36 homes · started 17 Feb 2020 · source

  7. Derryounce Estate

    Derryounce Estate, Portarlington, Laois, R32 A2R1 · Graiguecullen-Portarlington · 0.00 ha · 21 homes · started 31 Jul 2023 · source

  8. 10 Dwelling Units at Pattison Estate

    Pattison's Estate, Mountmellick, Laois · Borris-in-Ossory-Mountmellick · 10 homes · started 7 Dec 2020 · source

Where they are

Source: Commencement and completion notices (National Building Control Office), checked 12 Oct 2026. Each row links to the record it came from.

Embed this on your site free, updates itself

Paste this into your page. It shows the count and the latest entries, and links back here.

Preview the widget

What this means for a buyer

Every building job lodges a commencement notice on the Building Control Management System before it starts, and new homes need a completion certificate on the register before they can be occupied (Building Control Regulations, as amended in 2014). A scheme with no completion long after its planned finish may have run out of money or stalled on a dispute. Its owner or lender may take an offer. Some are only slow or phased, so check the site.

Who holds these permissions: developers in Laois

Unbuilt permissions in Laois, scheme by scheme (Planning Register)

Questions people ask

What is a commencement notice?

The notice lodged on the Building Control Management System 14 to 28 days before works start. It is the public record that a permission was acted on.

What is a completion certificate?

The certificate of compliance on completion, which must be on the building control register before new homes can be occupied.

Does stalled mean abandoned?

Not always. Phased schemes, small jobs and missing paperwork also show up. The start date and the planned finish on each row help tell them apart.

Where does this list come from?

From the National Building Control Office's open data on commencement notices and completion certificates, matched to planning permissions.