Building sites that started and stopped in Meath commenced, not completed

Housing with a commencement notice but no completion certificate, largest first.

31 sites where building started and no completion certificate has followed

31 new this week

  • 1 ha in all
  • 2,454 homes
  • checked 14 Oct 2026

New this week

  1. Millbourne - Phase 2

    Nos. 68, 70, 72, 74, 76 to 83 inc., 85 & 87 Millbourne Drive, Ashbourne, Meath · Ashbourne · 117 homes · started 3 Sept 2014 · source

    117 homes; commenced 03 Sep 2014, no completion certificate, planned end Sep 2019

  2. Block A, Summerseat, Clonee, Co. Meath

    Summerseat, Clonee, Meath · Ratoath · 30 homes · started 4 Jan 2016 · source

    30 homes; commenced 04 Jan 2016, no completion certificate, planned end Nov 2016

  3. 1 & 2 Maydenhayes Road, Donacarney Little, Mornington, Meath

    Laytown-Bettystown · 225 homes · started 8 May 2015 · source

    225 homes; commenced 08 May 2015, no completion certificate, planned end Nov 2015

  4. Patrick McEntegart - House

    Ballinamore, Nobber, Meath · Kells · 11 homes · started 25 Aug 2016 · source

    11 homes; commenced 25 Aug 2016, no completion certificate, planned end Aug 2017

  5. Amir Niazi No.18 Kribensis Manor, Clonee, Co. Meath

    18 Kribensis Manor, Williamstown Stud, Clonee, Meath · Ratoath · 10 homes · started 22 Jun 2017 · source

    10 homes; commenced 22 Jun 2017, no completion certificate, planned end May 2018

Open all 31 on the map

Stalled builds in Meath, every Monday

The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.

26 more of 31

  1. Baker Hall - Duplex - BD11

    Bakerhall, Limekilnhill, Belmont, Academy Street, Navan, Meath · Navan · 544 homes · started 12 Oct 2022 · source

  2. 1, Effernock Crescent

    Effernock, Trim, Meath · Trim · 334 homes · started 28 Mar 2019 · source

  3. Jamestown, Ratoath, Co Meath

    Jamestown, Ratoath, Meath · Ratoath · 228 homes · started 1 Sept 2021 · source

  4. Millbourne Phase 2

    84, 86, 88 & 90 Millbourne Drive, Ashbourne, Meath · Ashbourne · 117 homes · started 4 Jul 2014 · source

  5. Millbourne

    Nos. 92 & 94 Millbourne Drive, Ashbourne, Meath · Ashbourne · 117 homes · started 13 Jun 2014 · source

  6. Dun Eimear - Phase 1

    Dun Eimear, Bettystown, Meath · Laytown-Bettystown · 115 homes · started 24 Mar 2017 · source

  7. Nos. 64 & 66 Millbourne Drive

    Nos. 64 & 66 Millbourne Drive, Ashbourne, Meath · Ashbourne · 114 homes · started 4 Mar 2015 · source

  8. Donacarney Little, Donacarney, Co. Meath

    Donacarney Little, Donacarney, Meath, 999 · Laytown-Bettystown · 0.01 ha · 67 homes · started 31 Oct 2018 · source

  9. Donacarney Little, Donacarney, Meath

    Laytown-Bettystown · 62 homes · started 21 Dec 2018 · source

  10. Donacarney Little, Donacarney, Meath

    Laytown-Bettystown · 62 homes · started 14 Dec 2018 · source

  11. Kilcarn Woods, Navan, Co Meath

    Kilcarn Woods, Navan, Co Meath, Navan, Meath · Navan · 51 homes · started 27 Apr 2023 · source

  12. Kilcarn Woods

    Kilcarn Woods 2, Navan, Meath · Navan · 51 homes · started 12 May 2022 · source

  13. Maelduin, Dunshaughlin

    Maelduin, Dunshaughlin, Meath · Ratoath · 24 homes · started 10 Aug 2018 · source

  14. 7 The Burrows Killeen Castle

    7 The Burrows, Killeen Castle, Clavinstown, Meath · Ratoath · 0.01 ha · 22 homes · started 1 Feb 2022 · source

  15. Phase 1A of Housing development at Commons Road, Navan

    Commons Road, Navan, Meath · Navan · 20 homes · started 4 Jul 2018 · source

  16. 19194 Rathmoylan

    The Terrace, Rathmolyon, Meath, A83 T970 · Trim · 0.65 ha · 16 homes · started 27 Aug 2021 · source

  17. 19194 Rathmoylan

    Glebe Td, Rathmolyon, Meath · Trim · 0.01 ha · 16 homes · started 5 May 2021 · source

  18. The Cedars, Avourwen, Platin Road, Droghdea, Co. Meath

    Platin Road, Drogheda, Louth · Drogheda Urban · 16 homes · started 25 Aug 2014 · source

  19. Fairlands - Dunboyne

    Summerhill Road, Dunboyne, Meath · Ratoath · 15 homes · started 22 Aug 2016 · source

  20. The Green, Summerhill, Meath

    Trim · 13 homes · started 15 Jun 2018 · source

  21. The Green, Summerhill, Cavan

    Trim · 13 homes · started 15 Jun 2018 · source

  22. The Green, Summerhill, Meath

    Trim · 13 homes · started 14 Mar 2018 · source

  23. Emmet Street, Trim, Meath

    Trim · 11 homes · started 13 Sept 2021 · source

  24. Painestown two storey Dwelling

    60 Unnamed Road, Castletown Kilpatrick, Meath · Kells · 0.01 ha · 10 homes · started 14 Jul 2018 · source

  25. Abdul Rauf No.35 Kribensis Manor, Clonee, Co. Meath

    35 Kribensis Manor, Williamstown Stud, Clonee, Meath · Ratoath · 10 homes · started 20 Jun 2017 · source

  26. New bedroom block at Tankardstown

    Tankardstown House Rathkenny Co. Meath, Rathkenny, Meath · Laytown-Bettystown · 0.01 ha · started 25 Feb 2022 · source

Where they are

Source: Commencement and completion notices (National Building Control Office), checked 14 Oct 2026. Each row links to the record it came from.

Embed this on your site free, updates itself

Paste this into your page. It shows the count and the latest entries, and links back here.

Preview the widget

What this means for a buyer

Every building job lodges a commencement notice on the Building Control Management System before it starts, and new homes need a completion certificate on the register before they can be occupied (Building Control Regulations, as amended in 2014). A scheme with no completion long after its planned finish may have run out of money or stalled on a dispute. Its owner or lender may take an offer. Some are only slow or phased, so check the site.

Who holds these permissions: developers in Meath

Unbuilt permissions in Meath, scheme by scheme (Planning Register)

Questions people ask

What is a commencement notice?

The notice lodged on the Building Control Management System 14 to 28 days before works start. It is the public record that a permission was acted on.

What is a completion certificate?

The certificate of compliance on completion, which must be on the building control register before new homes can be occupied.

Does stalled mean abandoned?

Not always. Phased schemes, small jobs and missing paperwork also show up. The start date and the planned finish on each row help tell them apart.

Where does this list come from?

From the National Building Control Office's open data on commencement notices and completion certificates, matched to planning permissions.