Building sites that started and stopped in Wexford commenced, not completed

Housing with a commencement notice but no completion certificate, largest first.

16 sites where building started and no completion certificate has followed

16 new this week

  • 111 ha in all
  • 927 homes
  • checked 12 Oct 2026

New this week

  1. Gorey Hill Co Wexford

    Carnew Road, Gorey, Wexford · Gorey · 1.95 ha · 58 homes · started 20 Aug 2018 · source

    58 homes; commenced 20 Aug 2018, no completion certificate, planned end Nov 2018

  2. Lakeland, Bridgetown, Wexford

    Rosslare · 0.47 ha · 12 homes · started 9 Sept 2019 · source

    12 homes; commenced 09 Sep 2019, no completion certificate, planned end Aug 2020

  3. Mulgannon, Wexford

    Wexford · 15 ha · 181 homes · started 15 Aug 2017 · source

    181 homes; commenced 15 Aug 2017, no completion certificate, planned end Oct 2017

  4. Ramstown lower, Gorey, Wexford

    Gorey · 34 homes · started 27 Feb 2015 · source

    34 homes; commenced 27 Feb 2015, no completion certificate, planned end Feb 2017

  5. Salville Park

    KILLAGOLEY, Enniscorthy, Wexford, Y21 X2K8 · Enniscorthy · 11 ha · 71 homes · started 16 Nov 2020 · source

    71 homes; commenced 16 Nov 2020, no completion certificate, planned end Dec 2022

Open all 16 on the map

Stalled builds in Wexford, every Monday

The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.

11 more of 16

  1. 1A & 1B Oak Drive Deerpark,Fort Road Gorey

    Fort Road, Gorey, Wexford · Gorey · 297 homes · started 24 May 2023 · source

  2. Gorey Hill - 83 residential units / clubhouse & creche

    10 Westhill Park, Gorey, Wexford · Gorey · 3.56 ha · 83 homes · started 5 May 2021 · source

  3. CREAGH DEMESNE & GOREY CORPORATION LANDS, GOREY URBAN, Wexford

    CREAGH DEMESNE & GOREY CORPORATION LANDS,, GOREY URBAN, Wexford · Gorey · 38 homes · started 10 Apr 2015 · source

  4. Phase 3 - Castlelands

    Enniscorthy Road, Ferns, Wexford · Enniscorthy · 1.16 ha · 34 homes · started 7 Oct 2022 · source

  5. Castlelands Phase 4

    Enniscorthy Road, Ferns, Wexford · Enniscorthy · 1.16 ha · 34 homes · started 30 Oct 2020 · source

  6. Of 34no. dwellings at Ramstown Lower, Gorey

    ramstown lower, gorey, Wexford · Gorey · 34 homes · started 12 Dec 2014 · source

  7. Whiterock Hill, Wexford

    Wexford · 18 homes · started 25 Jul 2014 · source

  8. Dermot Corrigan (Dcl) - 12 New Dwellings

    LAKE, BRIDGETOWN, Wexford · Enniscorthy · 12 homes · started 30 Jan 2017 · source

  9. Colin and Lisa Garry

    Martingale, Edermine, Martingale, Edermine, Wexford, Wexford · Kilmuckridge · 0.24 ha · 11 homes · started 14 Jul 2022 · source

  10. NBCO TEST PLEASE IGNORE 20210703 KM CNwCD I

    Street, Town, Wexford · Birr · 10 homes · started 17 Jul 2021 · source

  11. Integrated Holiday Complex

    Kilmacoe, Curracloe, Wexford · Wexford · 76 ha · started 28 Mar 2022 · source

Where they are

Source: Commencement and completion notices (National Building Control Office), checked 12 Oct 2026. Each row links to the record it came from.

Embed this on your site free, updates itself

Paste this into your page. It shows the count and the latest entries, and links back here.

Preview the widget

What this means for a buyer

Every building job lodges a commencement notice on the Building Control Management System before it starts, and new homes need a completion certificate on the register before they can be occupied (Building Control Regulations, as amended in 2014). A scheme with no completion long after its planned finish may have run out of money or stalled on a dispute. Its owner or lender may take an offer. Some are only slow or phased, so check the site.

Who holds these permissions: developers in Wexford

Unbuilt permissions in Wexford, scheme by scheme (Planning Register)

Questions people ask

What is a commencement notice?

The notice lodged on the Building Control Management System 14 to 28 days before works start. It is the public record that a permission was acted on.

What is a completion certificate?

The certificate of compliance on completion, which must be on the building control register before new homes can be occupied.

Does stalled mean abandoned?

Not always. Phased schemes, small jobs and missing paperwork also show up. The start date and the planned finish on each row help tell them apart.

Where does this list come from?

From the National Building Control Office's open data on commencement notices and completion certificates, matched to planning permissions.