Building sites that started and stopped in Wexford commenced, not completed
Housing with a commencement notice but no completion certificate, largest first.
16 sites where building started and no completion certificate has followed
16 new this week
- 111 ha in all
- 927 homes
- checked 12 Oct 2026
New this week
Gorey Hill Co Wexford
Carnew Road, Gorey, Wexford · Gorey · 1.95 ha · 58 homes · started 20 Aug 2018 · source
58 homes; commenced 20 Aug 2018, no completion certificate, planned end Nov 2018
Lakeland, Bridgetown, Wexford
Rosslare · 0.47 ha · 12 homes · started 9 Sept 2019 · source
12 homes; commenced 09 Sep 2019, no completion certificate, planned end Aug 2020
Mulgannon, Wexford
Wexford · 15 ha · 181 homes · started 15 Aug 2017 · source
181 homes; commenced 15 Aug 2017, no completion certificate, planned end Oct 2017
Ramstown lower, Gorey, Wexford
Gorey · 34 homes · started 27 Feb 2015 · source
34 homes; commenced 27 Feb 2015, no completion certificate, planned end Feb 2017
Salville Park
KILLAGOLEY, Enniscorthy, Wexford, Y21 X2K8 · Enniscorthy · 11 ha · 71 homes · started 16 Nov 2020 · source
71 homes; commenced 16 Nov 2020, no completion certificate, planned end Dec 2022
Stalled builds in Wexford, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
11 more of 16
1A & 1B Oak Drive Deerpark,Fort Road Gorey
Fort Road, Gorey, Wexford · Gorey · 297 homes · started 24 May 2023 · source
Gorey Hill - 83 residential units / clubhouse & creche
10 Westhill Park, Gorey, Wexford · Gorey · 3.56 ha · 83 homes · started 5 May 2021 · source
CREAGH DEMESNE & GOREY CORPORATION LANDS, GOREY URBAN, Wexford
CREAGH DEMESNE & GOREY CORPORATION LANDS,, GOREY URBAN, Wexford · Gorey · 38 homes · started 10 Apr 2015 · source
Phase 3 - Castlelands
Enniscorthy Road, Ferns, Wexford · Enniscorthy · 1.16 ha · 34 homes · started 7 Oct 2022 · source
Castlelands Phase 4
Enniscorthy Road, Ferns, Wexford · Enniscorthy · 1.16 ha · 34 homes · started 30 Oct 2020 · source
Of 34no. dwellings at Ramstown Lower, Gorey
ramstown lower, gorey, Wexford · Gorey · 34 homes · started 12 Dec 2014 · source
Whiterock Hill, Wexford
Wexford · 18 homes · started 25 Jul 2014 · source
Dermot Corrigan (Dcl) - 12 New Dwellings
LAKE, BRIDGETOWN, Wexford · Enniscorthy · 12 homes · started 30 Jan 2017 · source
Colin and Lisa Garry
Martingale, Edermine, Martingale, Edermine, Wexford, Wexford · Kilmuckridge · 0.24 ha · 11 homes · started 14 Jul 2022 · source
NBCO TEST PLEASE IGNORE 20210703 KM CNwCD I
Street, Town, Wexford · Birr · 10 homes · started 17 Jul 2021 · source
Integrated Holiday Complex
Kilmacoe, Curracloe, Wexford · Wexford · 76 ha · started 28 Mar 2022 · source
Where they are
Source: Commencement and completion notices (National Building Control Office), checked 12 Oct 2026. Each row links to the record it came from.
What this means for a buyer
Every building job lodges a commencement notice on the Building Control Management System before it starts, and new homes need a completion certificate on the register before they can be occupied (Building Control Regulations, as amended in 2014). A scheme with no completion long after its planned finish may have run out of money or stalled on a dispute. Its owner or lender may take an offer. Some are only slow or phased, so check the site.
Who holds these permissions: developers in Wexford
Unbuilt permissions in Wexford, scheme by scheme (Planning Register)
Questions people ask
What is a commencement notice?
The notice lodged on the Building Control Management System 14 to 28 days before works start. It is the public record that a permission was acted on.
What is a completion certificate?
The certificate of compliance on completion, which must be on the building control register before new homes can be occupied.
Does stalled mean abandoned?
Not always. Phased schemes, small jobs and missing paperwork also show up. The start date and the planned finish on each row help tell them apart.
Where does this list come from?
From the National Building Control Office's open data on commencement notices and completion certificates, matched to planning permissions.