Where are the stalled building sites in South West Inner City?
19 building sites in South West Inner City started work but have no completion certificate, 204 homes in all, as of 26 Sep 2026. Each has a commencement notice with the National Building Control Office and is past its planned finish date.
From public registers, checked 26 Sep 2026. Updated nightly.
Stalled builds in South West Inner City, largest first
Brookfield Road, Kilmainham, Dublin 8
South West Inner City · Dublin City · 0.26 ha · source
Stalled build
79 homes; commenced 24 May 2023, no completion certificate, planned end Aug 2023
Brookefield Heights, Saint James', Kilmainham, Dublin 8
South West Inner City · Dublin City · 0.26 ha · source
Stalled build
79 homes; commenced 29 Jul 2023, no completion certificate, planned end Mar 2025
Enabling Works for Islandbridge Bellevue Apartments
South West Inner City · Dublin City · source
Stalled build
29 homes; commenced 18 Sep 2017, no completion certificate, planned end Oct 2017
Kilmainham 01
South West Inner City · Dublin City · 0.14 ha · source
Stalled build
17 homes; commenced 24 Feb 2020, no completion certificate, planned end Apr 2020
Eight Building - Infineon, 13-14 Newmarket, The Liberties, Dublin 8
South West Inner City · Dublin City · 0.24 ha · source
Stalled build
commenced 09 Dec 2021, no completion certificate, planned end Mar 2022
75-78 Cork Street, Dublin 8
South West Inner City · Dublin City · source
Stalled build
commenced 06 Aug 2020, no completion certificate, planned end Oct 2020
Ardee St, Newmarket Square
South West Inner City · Dublin City · 0.24 ha · source
Stalled build
commenced 16 May 2023, no completion certificate, planned end Jul 2023
The Donnelly Centre, Cork Street,Merchants Quay, Dublin 8
South West Inner City · Dublin City · source
Stalled build
commenced 23 Mar 2018, no completion certificate, planned end May 2018
St James's Hospital, Dublin 8, Dublin
South West Inner City · Dublin City · 0.02 ha · source
Stalled build
commenced 04 Jan 2021, no completion certificate, planned end Jul 2021
90 Elford Terrace, Donore Avenue
South West Inner City · Dublin City · 0.02 ha · source
Stalled build
0 homes; commenced 08 Apr 2020, no completion certificate, planned end Jun 2020
Ardee Point Student Accommodation Enabling Works
South West Inner City · Dublin City · source
Stalled build
commenced 08 May 2020, no completion certificate, planned end Sep 2020
Rear of 26, 27, 28, 29, New Row South, Dublin 8.
South West Inner City · Dublin City · source
Stalled build
0 homes; commenced 06 Aug 2018, no completion certificate, planned end Dec 2019
New Children's Hospital
South West Inner City · Dublin City · source
Stalled build
commenced 31 Jan 2019, no completion certificate, planned end Aug 2022
Children's Hospital, James's Street, Dublin 8
South West Inner City · Dublin City · source
Stalled build
commenced 15 Jun 2018, no completion certificate, planned end Jun 2019
Parexel
South West Inner City · Dublin City · source
Stalled build
commenced 18 Nov 2021, no completion certificate, planned end Jan 2022
22 Blackpitts
South West Inner City · Dublin City · source
Stalled build
commenced 11 Jul 2023, no completion certificate, planned end Oct 2023
14-15 City Gate, St Augustine Street, Dublin 8
South West Inner City · Dublin City · source
Stalled build
commenced 10 Dec 2019, no completion certificate, planned end Jan 2020
Enabling Works: 42 Parkgate Street - Phase 1
South West Inner City · Dublin City · source
Stalled build
commenced 07 Apr 2021, no completion certificate, planned end May 2021
The Donnelly Centre, 25 Cork Street, Dublin 8, Dublin
South West Inner City · Dublin City · source
Stalled build
commenced 27 Mar 2019, no completion certificate, planned end May 2019
Go further
New development sites in Dublin City, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
More about South West Inner City
- Is there development land for sale in South West Inner City?
- Buildable found 60 sites in South West Inner City with a public sign they could come to market, as of 26 Sep 2026: 3 council sites proposed for sale, 8 sites with planning permission running out or recently expired, 32 derelict sites on the register and 19 stalled builds. These come from public registers, not agents' listings, so many are not advertised yet.
- How many development sites are there in South West Inner City?
- Buildable tracks 422 development sites in South West Inner City, as of 26 Sep 2026: every site with a public reason it could be built on or sold, from the councils' and national registers. They include 2 permissions running out, 10 permitted schemes not started, 34 derelict sites, 3 council land sales and 19 stalled builds.
- What are the largest development sites in South West Inner City?
- 57 development sites in South West Inner City are a hectare or larger, as of 26 Sep 2026. The largest is public land in South West Inner City, at 32.7 ha (publicly owned land).
- Where are the derelict sites in South West Inner City?
- South West Inner City has 32 sites on the council's derelict sites register, as of 26 Sep 2026. The owner of a registered site pays a levy of 7% of its market value a year.
Data as of 26 Sep 2026. Sources: Commencement and completion notices (National Building Control Office).
Cite this: Where are the stalled building sites in South West Inner City? Buildable, data as of 26 Sep 2026. https://buildable.ie/q/stalled-building-sites-south-west-inner-city
Facts from public registers, not advice. Every question · How it works