1. St Patrick's CourtNew
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 45 days10 homes0.87 haLongford
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 45 days10 homes0.87 haLongford
Permission running out
26 homes granted 9 Aug 2022, expires 8 Aug 2027, not started source
Expires in 296 days26 homes1.85 haOffaly
Was this site new to you?
Stalled build
Granted with no commencement: 117 homes; commenced 03 Sep 2014, no completion certificate, planned end Sep 2019 source
117 homesMeath
Stalled build
Granted with no commencement: 225 homes; commenced 08 May 2015, no completion certificate, planned end Nov 2015 source
225 homesMeath
Stalled build
Granted with no commencement: 544 homes; commenced 12 Oct 2022, no completion certificate, planned end Jul 2023 source
544 homesMeath
Stalled build
Granted with no commencement: 114 homes; commenced 04 Mar 2015, no completion certificate, planned end Jan 2019 source
114 homesMeath
Stalled build
Granted with no commencement: 117 homes; commenced 04 Jul 2014, no completion certificate source
117 homesMeath
Stalled build
Granted with no commencement: 16 homes; commenced 27 Aug 2021, no completion certificate, planned end Apr 2022 source
16 homes0.65 haMeath
Stalled build
Granted with no commencement: 117 homes; commenced 13 Jun 2014, no completion certificate source
117 homesMeath
Stalled build
Granted with no commencement: 31 homes; commenced 26 Apr 2018, no completion certificate, planned end Aug 2019 source
31 homes1.55 haLongford
Stalled build
Granted with no commencement: 12 homes; commenced 03 Sep 2018, no completion certificate, planned end Sep 2019 source
12 homes2.09 haLongford
Stalled build
Granted with no commencement: 10 homes; commenced 08 Apr 2020, no completion certificate, planned end Dec 2020 source
10 homes0.80 haWestmeath
36 homes1.03 haWestmeath
Stalled build
Granted with no commencement: 39 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
39 homes3.30 haFingal
Stalled build
Granted with no commencement: 55 homes; commenced 30 Mar 2023, no completion certificate, planned end Dec 2023 source
55 homes1.35 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Sep 2024 source
15 homes2.79 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 198 homes; commenced 23 May 2022, no completion certificate, planned end Dec 2023 source
198 homes0.77 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 08 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 180 homes; commenced 05 Sep 2023, no completion certificate, planned end Mar 2024 source
180 homes1.42 haFingal
Stalled build
Granted with no commencement: 88 homes; commenced 22 Oct 2021, no completion certificate, planned end Oct 2022 source
88 homes0.63 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Jul 2023 source
15 homes3.30 haFingal