1. St Patrick's CourtNew
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 41 days10 homes0.87 haLongford
Permission running out
10 homes granted 1 Dec 2021, expires 30 Nov 2026, not started source
Expires in 41 days10 homes0.87 haLongford
Derelict siteOn the RZLT map (3% land tax)On the RZLT map, no permission
On the council's derelict sites register: Register ref 1726, entered 16 Feb 2015, market value €145,000 source
18–51 homes0.65 haSouth Dublin
Permission running out
45 homes granted 30 Mar 2022, expires 29 Mar 2027, not started source
Expires in 160 days45 homes2.28 haWexford
Was this site new to you?
Stalled build
Granted with no commencement: 31 homes; commenced 26 Apr 2018, no completion certificate, planned end Aug 2019 source
31 homes1.55 haLongford
Stalled build
Granted with no commencement: 12 homes; commenced 03 Sep 2018, no completion certificate, planned end Sep 2019 source
12 homes2.09 haLongford
Stalled build
Granted with no commencement: 114 homes; commenced 11 Jun 2018, no completion certificate, planned end Oct 2018 source
114 homes0.59 haSouth Dublin
Stalled build
Granted with no commencement: 93 homes; commenced 25 Apr 2022, no completion certificate, planned end Apr 2024 source
93 homes2.15 haSouth Dublin
Stalled build
Granted with no commencement: 12 homes; commenced 22 Aug 2022, no completion certificate, planned end Aug 2023 source
12 homes3.25 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 16 homes; commenced 04 Jan 2022, no completion certificate, planned end Jan 2024 source
16 homes3.25 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 25 homes; commenced 04 Jan 2022, no completion certificate, planned end Jan 2024 source
25 homes3.25 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 172 homes; commenced 27 Sep 2023, no completion certificate, planned end Aug 2024 source
172 homes0.55 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 172 homes; commenced 27 Sep 2023, no completion certificate, planned end Aug 2024 source
172 homes0.55 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 38 homes; commenced 10 Apr 2015, no completion certificate, planned end Oct 2015 source
38 homesWexford
Stalled build
Granted with no commencement: 23 homes; commenced 03 Jan 2023, no completion certificate, planned end Jun 2024 source
23 homes0.43 haLongford
Stalled build
Granted with no commencement: 34 homes; commenced 07 Oct 2022, no completion certificate, planned end May 2023 source
34 homes1.16 haWexford
Was this site new to you?
Stalled build
Granted with no commencement: 34 homes; commenced 30 Oct 2020, no completion certificate, planned end Jun 2021 source
34 homes1.16 haWexford
Was this site new to you?
Stalled build
Granted with no commencement: 297 homes; commenced 24 May 2023, no completion certificate, planned end Dec 2023 source
297 homesWexford
Was this site new to you?
Derelict siteOn the RZLT map (3% land tax)On the RZLT map, no permission
On the council's derelict sites register: Register ref 1940, entered 02 Oct 2024, market value €475,000 source
3–10 homes0.13 haSouth Dublin
Stalled build
Granted with no commencement: 12 homes; commenced 12 May 2015, no completion certificate, planned end May 2020 source
12 homes0.27 haSouth Dublin
Stalled build
Granted with no commencement: 12 homes; commenced 21 Oct 2014, no completion certificate, planned end Aug 2017 source
12 homes3.48 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 16 homes; commenced 18 Mar 2015, no completion certificate, planned end Feb 2016 source
16 homes0.50 haSouth Dublin
Stalled build
Granted with no commencement: 14 homes; commenced 30 Oct 2014, no completion certificate, planned end Jan 2016 source
14 homes0.47 haSouth Dublin
Stalled build
Granted with no commencement: 12 homes; commenced 28 Aug 2014, no completion certificate, planned end Aug 2017 source
12 homes3.48 haSouth Dublin
Was this site new to you?
Stalled build
Granted with no commencement: 578 homes; commenced 25 Aug 2023, no completion certificate, planned end Oct 2024 source
578 homes28.5 haSouth Dublin