1. Phase 1A Housing Development at Tipper West, Blessington RoadNew
Stalled build
Granted with no commencement: 385 homes; commenced 10 Aug 2021, no completion certificate, planned end Sep 2022 source
385 homesKildare
Stalled build
Granted with no commencement: 385 homes; commenced 10 Aug 2021, no completion certificate, planned end Sep 2022 source
385 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 05 Jul 2021, no completion certificate, planned end Feb 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 28 Apr 2021, no completion certificate, planned end Oct 2021 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 14 Oct 2021, no completion certificate, planned end Jul 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 30 Jul 2021, no completion certificate, planned end Jul 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 152 homes; commenced 04 Aug 2021, no completion certificate, planned end Jun 2022 source
152 homesKildare
Stalled build
Granted with no commencement: 10 homes; commenced 08 Apr 2020, no completion certificate, planned end Dec 2020 source
10 homes0.80 haWestmeath
36 homes1.03 haWestmeath
Stalled build
Granted with no commencement: 39 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
39 homes3.30 haFingal
Stalled build
Granted with no commencement: 55 homes; commenced 30 Mar 2023, no completion certificate, planned end Dec 2023 source
55 homes1.35 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Sep 2024 source
15 homes2.79 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 198 homes; commenced 23 May 2022, no completion certificate, planned end Dec 2023 source
198 homes0.77 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 08 Sep 2022, no completion certificate, planned end Mar 2024 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 180 homes; commenced 05 Sep 2023, no completion certificate, planned end Mar 2024 source
180 homes1.42 haFingal
Stalled build
Granted with no commencement: 88 homes; commenced 22 Oct 2021, no completion certificate, planned end Oct 2022 source
88 homes0.63 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 20 Sep 2022, no completion certificate, planned end Jul 2023 source
15 homes3.30 haFingal
Stalled build
Granted with no commencement: 15 homes; commenced 31 Mar 2023, no completion certificate, planned end Mar 2025 source
15 homes3.29 haFingal
Stalled build
Granted with no commencement: 39 homes; commenced 20 Sep 2022, no completion certificate, planned end Sep 2024 source
39 homes2.79 haFingal
Stalled build
Granted with no commencement: 26 homes; commenced 05 Aug 2014, no completion certificate, planned end Jul 2015 source
26 homes1.55 haFingal
Stalled build
Granted with no commencement: 26 homes; commenced 22 Oct 2014, no completion certificate, planned end Sep 2019 source
26 homes1.36 haFingal
Stalled build
Granted with no commencement: 35 homes; commenced 20 Apr 2015, no completion certificate, planned end Nov 2015 source
35 homes1.46 haFingal