Dublin planning permissions expiring
31 Dublin sites have a planning permission for 10 or more homes that expires in the next 12 months with no start: 5,738 homes. Another 50, with 9,511 homes, expired unbuilt since 10 October 2024.
Updated 7 October 2026. Counted from the 81 sites on the permissions running out list, for the 12 months to 7 October 2027.
- 31sites with a permission running out in 12 months, not started
- 5,738homes in those permissions
- 50expired unbuilt since 10 October 2024
- 9,511homes in the expired permissions
By council
| Council | Running out, 12 months | Homes | Expired, not started | Homes |
|---|---|---|---|---|
| Dublin City | 19 | 3,763 | 29 | 6,672 |
| Dún Laoghaire-Rathdown | 8 | 1,150 | 4 | 577 |
| Fingal | 2 | 273 | 11 | 1,707 |
| South Dublin | 2 | 552 | 6 | 555 |
| Dublin | 31 | 5,738 | 50 | 9,511 |
By month
The months as a table
| Month | Sites | Homes |
|---|---|---|
| Oct 2026 | 0 | 0 |
| Nov 2026 | 5 | 1,967 |
| Dec 2026 | 4 | 568 |
| Jan 2027 | 1 | 19 |
| Feb 2027 | 3 | 263 |
| Mar 2027 | 2 | 409 |
| Apr 2027 | 2 | 504 |
| May 2027 | 3 | 247 |
| Jun 2027 | 2 | 113 |
| Jul 2027 | 1 | 358 |
| Aug 2027 | 6 | 1,070 |
| Sept 2027 | 2 | 220 |
| Oct 2027 | 0 | 0 |
The largest running out
- Holy Cross College · 1,614 homes · expires 4 November 2026
- Brewery Road and Leopardstown Road · 463 homes · expires 13 April 2027
- Cooldown Commons and Fortunestown · 421 homes · expires 10 August 2027
- Heuston South Quarter · 399 homes · expires 31 March 2027
- Cunningham House · 358 homes · expires 4 July 2027
Cite this
When you quote a number, please name Buildable and link to this page.
How it’s counted
A site counts as running out when it has a planning permission for 10 or more homes that expires within the next 12 months and no commencement notice has been lodged for it. It counts as expired when that permission ended in the last two years without a start. Each site is one permission; one replaced by a later grant, or still under appeal, is left out. A permission lasts five years from the grant unless it says otherwise (Planning and Development Act 2000, s.40). Homes are the number granted.
A commencement notice can be missing or matched to the wrong permission, and an extension of duration may not yet show in the data, so check the planning file before relying on a single site. This is a count of public records, not a view on any site’s value.
Sources: Planning applications (Department of Housing national planning data): grant dates, number of homes, the permission's duration; Commencement notices (National Building Control Office, BCMS): whether a start was lodged. Each site’s page links its planning record. Checked 7 October 2026.
What an owner can still do before a permission expires · The list, site by site · Dublin Development Land Index
Permissions running out in Dublin, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.