Dublin planning permissions expiring

31 Dublin sites have a planning permission for 10 or more homes that expires in the next 12 months with no start: 5,738 homes. Another 50, with 9,511 homes, expired unbuilt since 10 October 2024.

Updated 7 October 2026. Counted from the 81 sites on the permissions running out list, for the 12 months to 7 October 2027.

By council

CouncilRunning out, 12 monthsHomesExpired, not startedHomes
Dublin City193,763296,672
Dún Laoghaire-Rathdown81,1504577
Fingal2273111,707
South Dublin25526555
Dublin315,738509,511

Download the figures by council and month (CSV)

By month

Oct 2026: 0 homes, 0 sitesOct ’26Nov 2026: 1,967 homes, 5 sites1,967NovDec 2026: 568 homes, 4 sitesDecJan 2027: 19 homes, 1 siteJan ’27Feb 2027: 263 homes, 3 sitesFebMar 2027: 409 homes, 2 sitesMarApr 2027: 504 homes, 2 sitesAprMay 2027: 247 homes, 3 sitesMayJun 2027: 113 homes, 2 sitesJunJul 2027: 358 homes, 1 siteJulAug 2027: 1,070 homes, 6 sitesAugSept 2027: 220 homes, 2 sitesSeptOct 2027: 0 homes, 0 sitesOct
Homes in permissions running out unstarted, by month of expiry, Oct 2026 to Oct 2027
The months as a table
MonthSitesHomes
Oct 202600
Nov 202651,967
Dec 20264568
Jan 2027119
Feb 20273263
Mar 20272409
Apr 20272504
May 20273247
Jun 20272113
Jul 20271358
Aug 202761,070
Sept 20272220
Oct 202700

The largest running out

  1. Holy Cross College · 1,614 homes · expires 4 November 2026
  2. Brewery Road and Leopardstown Road · 463 homes · expires 13 April 2027
  3. Cooldown Commons and Fortunestown · 421 homes · expires 10 August 2027
  4. Heuston South Quarter · 399 homes · expires 31 March 2027
  5. Cunningham House · 358 homes · expires 4 July 2027

Every site, soonest first

Cite this

When you quote a number, please name Buildable and link to this page.

How it’s counted

A site counts as running out when it has a planning permission for 10 or more homes that expires within the next 12 months and no commencement notice has been lodged for it. It counts as expired when that permission ended in the last two years without a start. Each site is one permission; one replaced by a later grant, or still under appeal, is left out. A permission lasts five years from the grant unless it says otherwise (Planning and Development Act 2000, s.40). Homes are the number granted.

A commencement notice can be missing or matched to the wrong permission, and an extension of duration may not yet show in the data, so check the planning file before relying on a single site. This is a count of public records, not a view on any site’s value.

Sources: Planning applications (Department of Housing national planning data): grant dates, number of homes, the permission's duration; Commencement notices (National Building Control Office, BCMS): whether a start was lodged. Each site’s page links its planning record. Checked 7 October 2026.

What an owner can still do before a permission expires · The list, site by site · Dublin Development Land Index

Embed this on your site free, updates itself

Paste this into your page. It shows the count and the latest entries, and links back here.

Preview the widget

Permissions running out in Dublin, every Monday

The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.