Site known as Leonard's Corner - No.s 52
Dublin City · 19 homes
Register ref DS1280B, entered 11 Jun 2024
Source: services-eu1.arcgis.com ↗New signals on development sites, newest first. Every one links to its source.
Dublin City · 19 homes
Register ref DS1280B, entered 11 Jun 2024
Source: services-eu1.arcgis.com ↗Dublin City · 940 m² · 12 homes
12 homes granted 24 Sep 2021, expires 24 Sep 2026
Source: services.arcgis.com ↗Dublin City · 940 m² · 12 homes
12 homes granted 24 Sep 2021, expires 24 Sep 2026
Source: services.arcgis.com ↗Dublin City · 0.53 ha
commenced 12 Dec 2022, no completion certificate, planned end Apr 2023
Source: data.nbco.gov.ie ↗Dublin City · 250 m² · 1 home
1 homes; commenced 09 Jul 2020, no completion certificate, planned end Jul 2021
Source: data.nbco.gov.ie ↗Dublin City
commenced 20 Jul 2018, no completion certificate, planned end Dec 2018
Source: data.nbco.gov.ie ↗Dublin City
commenced 02 May 2023, no completion certificate, planned end Oct 2023
Source: data.nbco.gov.ie ↗Dublin City · 100 m²
commenced 15 Jun 2022, no completion certificate, planned end Jul 2022
Source: data.nbco.gov.ie ↗The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
Dublin City
commenced 23 Oct 2018, no completion certificate, planned end Apr 2019
Source: data.nbco.gov.ie ↗Dublin City
commenced 14 Jan 2019, no completion certificate, planned end Apr 2019
Source: data.nbco.gov.ie ↗Dublin City
commenced 03 Jul 2018, no completion certificate, planned end Oct 2018
Source: data.nbco.gov.ie ↗Dublin City · 166 homes
166 homes; commenced 23 Jan 2015, no completion certificate, planned end Jan 2016
Source: data.nbco.gov.ie ↗Dublin City
commenced 25 Oct 2019, no completion certificate, planned end Apr 2020
Source: data.nbco.gov.ie ↗Dublin City
commenced 24 Nov 2020, no completion certificate, planned end Dec 2020
Source: data.nbco.gov.ie ↗Dublin City · 850 m²
commenced 29 Mar 2022, no completion certificate, planned end Aug 2022
Source: data.nbco.gov.ie ↗Dublin City
commenced 06 Jul 2020, no completion certificate, planned end Jul 2021
Source: data.nbco.gov.ie ↗Dublin City · 0.37 ha · 10–29 homes
commenced 11 Feb 2022, no completion certificate, planned end May 2022
Source: data.nbco.gov.ie ↗Dublin City · 980 m²
commenced 30 Sep 2020, no completion certificate, planned end Oct 2020
Source: data.nbco.gov.ie ↗Dublin City
commenced 14 Dec 2018, no completion certificate, planned end Dec 2018
Source: data.nbco.gov.ie ↗Dublin City
commenced 28 Aug 2018, no completion certificate, planned end Oct 2018
Source: data.nbco.gov.ie ↗Dublin City · 1.64 ha
commenced 04 Apr 2022, no completion certificate, planned end Sep 2023
Source: data.nbco.gov.ie ↗Dublin City · 0.43 ha
commenced 02 Sep 2019, no completion certificate, planned end Jun 2020
Source: data.nbco.gov.ie ↗Dublin City · 25 homes
25 homes; commenced 02 Jan 2019, no completion certificate, planned end Jun 2020
Source: data.nbco.gov.ie ↗Dublin City · 0.81 ha · 22–64 homes
commenced 11 Nov 2019, no completion certificate, planned end Jun 2020
Source: data.nbco.gov.ie ↗Dublin City
commenced 04 Jun 2019, no completion certificate, planned end Sep 2019
Source: data.nbco.gov.ie ↗Dublin City
commenced 25 Oct 2021, no completion certificate, planned end Nov 2021
Source: data.nbco.gov.ie ↗Dublin City
commenced 09 Aug 2018, no completion certificate, planned end May 2019
Source: data.nbco.gov.ie ↗Dublin City · 0.43 ha · 12–34 homes
commenced 25 Jul 2019, no completion certificate, planned end Dec 2019
Source: data.nbco.gov.ie ↗Dublin City
commenced 08 Mar 2019, no completion certificate, planned end Jun 2019
Source: data.nbco.gov.ie ↗Dublin City
commenced 18 Sep 2018, no completion certificate, planned end Oct 2018
Source: data.nbco.gov.ie ↗Not seeing what you need? .