Tue 22 Sep · 1
Permission expiredHowth-Malahide, Fingal
Permission for 162 homes expired 22 Sept 2026 without a start.
The owner must apply again or sell. The principle is already established.
1.74 ha · 162 homes · Zoned RS · Residential
Also:Underused site
New development sites in Dublin, every Monday
The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
Ended lately (116)Permissions that started, sites off a register, notices closed
Sun 27 Sep
Stalled buildEndedClondalkin, South Dublin
South Dublin, D24 DH9Y
“commenced 12 Oct 2022, no completion certificate, planned end Jan 2023”
3.26 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedFirhouse-Bohernabreena, South Dublin
“commenced 18 Dec 2020, no completion certificate, planned end Jan 2021”
1.24 ha · 34–99 homes · Zoned DC · To protect, improve and provide for the future development of…
Stalled buildEndedRathfarnham-Templeogue, South Dublin
St. James Road / Limekiln Green, Dublin, D12 A02K
“commenced 09 Jul 2018, no completion certificate, planned end Aug 2018”
0.80 ha · 22–64 homes · Zoned LC · To protect, improve and provide for the future development of Local…
Stalled buildEndedRathfarnham-Templeogue, South Dublin
Orwell park, Dublin, D6W TF88
“commenced 04 Feb 2020, no completion certificate, planned end Dec 2020”
0.77 ha · 21–61 homes · Zoned LC · To protect, improve and provide for the future development of Local…
Stalled buildEndedRathfarnham-Templeogue, South Dublin
Ballymount Road Lower, Dublin, South Dublin, D12 RW10
“commenced 14 Sep 2020, no completion certificate, planned end May 2022”
1.14 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
Pfizer Grange Castle, Grange Castle international Business Park, Dublin, South Dublin, D22 V8F8
“commenced 30 Nov 2020, no completion certificate, planned end Feb 2022”
35.7 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedLucan, South Dublin
Weston Airport,, Backweston Park, Leixlip, South Dublin, W23 XHF8
“commenced 21 Aug 2023, no completion certificate, planned end Mar 2024”
0.73 ha · Zoned RU · To protect and improve rural amenity and to provide for the…
Stalled buildEndedTallaght Central, South Dublin
SERLA HOUSE HIBERNIAN INDUSTRIAL ESTATE, Dublin, South Dublin, D24 NX22
“commenced 11 Nov 2020, no completion certificate, planned end Nov 2020”
690 m² · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
South Dublin, D24 DH9Y
“commenced 18 Oct 2021, no completion certificate, planned end Mar 2022”
3.26 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedLucan, South Dublin
Adamstown, Lucan, Dublin
“commenced 14 Aug 2019, no completion certificate, planned end Dec 2020”
1.07 ha · 29–85 homes · Zoned SDZ · To provide for strategic development in accordance with approved…
Stalled buildEndedClondalkin, South Dublin
Main Street, Newcastle, Dublin 22, D22
“40 homes; commenced 01 Jul 2019, no completion certificate, planned end Sep 2019”
1.75 ha · 40 homes
Stalled buildEndedTallaght South, South Dublin
3007 Lake Drive, Citywest Business Campus,, Dublin, South Dublin, D24 N2HR
“commenced 09 Mar 2021, no completion certificate, planned end May 2021”
120 m² · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
74 Broadfield Avenue, Rathcoole, D24 PX01
“0 homes; commenced 14 Oct 2019, no completion certificate, planned end Oct 2019”
240 m² · Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedRathfarnham-Templeogue, South Dublin
Unit 2A, Smurfit Packaging Systems, Ballymount Road Lower, Dublin, D12 KD80
“commenced 14 Sep 2022, no completion certificate, planned end Nov 2022”
0.13 ha · 3–10 homes · Zoned REGEN · To facilitate enterprise and/or residential led regeneration
Stalled buildEndedPalmerstown-Fonthill, South Dublin
Fonthill Road Lucan Co Dublin, Dublin, South Dublin, D22WC63
“commenced 22 Feb 2021, no completion certificate, planned end Mar 2021”
Zoned RW · To provide for and consolidate retail warehousing
Stalled buildEndedClondalkin, South Dublin
“1 homes; commenced 08 Nov 2022, no completion certificate, planned end Mar 2023”
730 m² · 1 home · Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedRathfarnham-Templeogue, South Dublin
JFK Avenue, Dublin, South Dublin, D12 NX74
“commenced 18 Jul 2022, no completion certificate, planned end Jul 2022”
0.50 ha · 13–39 homes · Zoned REGEN · To facilitate enterprise and/or residential led regeneration
Stalled buildEndedClondalkin, South Dublin
New Nangor Road, Profile Park, South Dublin
“commenced 20 Apr 2023, no completion certificate, planned end Feb 2025”
8.76 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
Monastery Road, Dublin, South Dublin, D22 F8F5
“commenced 07 Dec 2022, no completion certificate, planned end Feb 2023”
Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedRathfarnham-Templeogue, South Dublin
2 Fonthill Park, Dublin
“1 homes; commenced 04 Jul 2018, no completion certificate, planned end Nov 2018”
320 m² · 1 home · Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedClondalkin, South Dublin
Profile Park Business Park, New Nangor Road, Dublin 22, South Dublin
“commenced 04 Aug 2023, no completion certificate, planned end Nov 2024”
8.76 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedTallaght South, South Dublin
2020 Bianconi Avenue, Dublin, Dublin 24, D24 T683
“commenced 10 Apr 2019, no completion certificate, planned end Apr 2019”
6.55 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
“commenced 21 Jul 2023, no completion certificate, planned end Sep 2023”
1.82 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedTallaght Central, South Dublin
“commenced 11 Nov 2022, no completion certificate, planned end Nov 2023”
Zoned REGEN · To facilitate enterprise and/or residential led regeneration
Stalled buildEndedTallaght South, South Dublin
Kingswood Avenue, Dublin, South Dublin, D24 W1HP
“commenced 30 Nov 2020, no completion certificate, planned end Jul 2021”
120 m² · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedPalmerstown-Fonthill, South Dublin
Fonthill Road, Dublin, Dublin 22, D22 KP89
“commenced 21 Mar 2019, no completion certificate, planned end Jun 2019”
1.08 ha · Zoned MRC · To protect, improve and provide for the future development of a Major…
Stalled buildEndedClondalkin, South Dublin
Site partially bounded by Profile Park road on the east, north and west., Profile Park, South Dublin
“commenced 04 Apr 2023, no completion certificate, planned end Apr 2024”
0.67 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedTallaght South, South Dublin
2050 Orchard Avenue, Dublin, D24 WKP2
“commenced 15 Aug 2019, no completion certificate, planned end Oct 2019”
0.10 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedSouth Dublin
Roselawn, Ballydowd,, Lucan,, South Dublin
“commenced 15 Aug 2022, no completion certificate, planned end Nov 2022”
Stalled buildEndedClondalkin, South Dublin
Newlands Cross, Dublin 22, D22 W324
“commenced 12 Dec 2019, no completion certificate, planned end Dec 2019”
0.18 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedSwords, Fingal
Unit D, North Dublin Corporate Park, Swords, Dublin, K67 W5P7
“commenced 12 Sep 2018, no completion certificate, planned end Nov 2018”
0.26 ha · 7–20 homes · Zoned MRE · Metro and Rail Economic Corridor
Stalled buildEndedRush-Lusk, Fingal
Knockarlow South Shore Road, Rush, Dublin
“1 homes; commenced 05 Apr 2019, no completion certificate, planned end Nov 2019”
0.24 ha · 1 home · Zoned RS · Residential
Stalled buildEndedSouth Dublin
Ballymount Road Upper, Ballymount, Dublin, D12 VFEO
“commenced 13 Dec 2018, no completion certificate, planned end Dec 2019”
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
10C Ballycoolin Road, Dublin, Fingal
“commenced 10 Feb 2023, no completion certificate, planned end May 2023”
1.20 ha · Zoned GE · General Employment
Stalled buildEndedBalbriggan, Fingal
20 New Street, Skerries, Dublin
“1 homes; commenced 20 Dec 2018, no completion certificate, planned end Dec 2019”
200 m² · 1 home · Zoned TC · Town and District Centre
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
BALLYCOOLIN BUSINESS PARK, BALLYCOOLIN ROAD, Dublin, Dublin 15, D15 VNC4
“commenced 20 Nov 2018, no completion certificate, planned end Dec 2019”
5.62 ha · Zoned HT · High Technology
Stalled buildEndedBalbriggan, Fingal
Rathmooney, Lusk, Fingal
“commenced 27 Sep 2022, no completion certificate, planned end Mar 2023”
2.54 ha · Zoned FP · Food Park
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Saint Margaret's Road, Harristown, Swords, Co Dublin, Dublin, K67 N6T7
“commenced 24 Feb 2020, no completion certificate, planned end May 2020”
3.67 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Hexagon Building, IDA Blanchardstown Business and Technology Park, Snugborough Road, Dublin, Fingal, D15 V978
“commenced 09 Jul 2021, no completion certificate, planned end Jan 2022”
Zoned HT · High Technology
Stalled buildEndedSwords, Fingal
Hertz - Swords Business Park, Swords, Dublin, K67 X903
“commenced 23 Nov 2018, no completion certificate, planned end Jan 2019”
Zoned MRE · Metro and Rail Economic Corridor
Stalled buildEndedCastleknock, Fingal
Diswellstown, Castleknock, Dublin 15
“12 homes; commenced 25 Sep 2017, no completion certificate, planned end Jul 2018”
1.31 ha · 12 homes · Zoned HA · High Amenity
Stalled buildEndedFingal
“commenced 25 Nov 2019, no completion certificate, planned end Jan 2020”
Stalled buildEndedCastleknock, Fingal
Clonsilla Road, Clonsilla, Dublin 15
“33 homes; commenced 23 Mar 2017, no completion certificate, planned end Jul 2017”
1.04 ha · 33 homes · Zoned RS · Residential
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
claremount, Coolquoy Common, Fingal
“commenced 23 Jul 2020, no completion certificate, planned end Sep 2020”
1.00 ha · Zoned RU · Rural
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
“455 homes; commenced 24 Jul 2015, no completion certificate, planned end Jul 2016”
28.5 ha · 455 homes · Zoned RS · Residential
Stalled buildEndedRush-Lusk, Fingal
North Hill, Rush
“commenced 13 Apr 2020, no completion certificate, planned end May 2020”
2.26 ha · Zoned RU · Rural
Stalled buildEndedRush-Lusk, Fingal
“1 homes; commenced 08 Nov 2018, no completion certificate, planned end Nov 2019”
0.19 ha · 1 home · Zoned HA · High Amenity
Stalled buildEndedSwords, Fingal
Malahide Road, Swords, Fingal, K67 YY15
“commenced 28 Feb 2022, no completion certificate, planned end Apr 2022”
6.83 ha · 191–546 homes · Zoned MC · Major Town Centre
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Unit D8, Horizon Logistics Park, Harristown, Swords, Co Dublin, Co Dublin, Fingal, K67 F5X6
“commenced 04 Jan 2022, no completion certificate, planned end Apr 2022”
3.39 ha · Zoned GE · General Employment
Stalled buildEndedCastleknock, Fingal
“commenced 09 Jun 2022, no completion certificate, planned end Jul 2022”
Zoned MC · Major Town Centre
Stalled buildEndedRush-Lusk, Fingal
Brook Lane, Rush, Fingal
“commenced 28 Sep 2021, no completion certificate, planned end Sep 2022”
2.26 ha · Zoned RU · Rural
Stalled buildEndedRush-Lusk, Fingal
Corduff, Lusk, Fingal
“commenced 15 Sep 2022, no completion certificate, planned end Dec 2022”
3.09 ha · Zoned RU · Rural
Stalled buildEndedBalbriggan, Fingal
Unit 8, Skerries Point Shopping Center, Kelly's Bay Parade, Skerries, Dublin, County Dublin
“commenced 02 Mar 2020, no completion certificate, planned end Jun 2020”
1.07 ha · 30–85 homes · Zoned LC · Local Centre
Stalled buildEndedCastleknock, Fingal
“1 homes; commenced 13 Aug 2018, no completion certificate, planned end Nov 2018”
0 m² · 1 home · Zoned RS · Residential
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
4 Damastown Close, Dublin, Fingal
“commenced 20 Jul 2022, no completion certificate, planned end Jul 2023”
1.06 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Saint Margaret's Park, Dublin 11, Fingal
“commenced 08 Mar 2021, no completion certificate, planned end Jul 2022”
4.88 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Blanchardstown Road North, Blanchardstown, Dublin
“1 homes; commenced 28 Jan 2022, no completion certificate, planned end Jan 2023”
0.78 ha · 1 home · Zoned CI · Community Infrastructure
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
27 Northwood Avenue, Northwood, Dublin
“12 homes; commenced 12 Mar 2020, no completion certificate, planned end Jun 2021”
0.39 ha · 12 homes · Zoned MRE · Metro and Rail Economic Corridor
Stalled buildEndedRush-Lusk, Fingal
R132, Lusk, Dublin
“commenced 17 Dec 2018, no completion certificate, planned end Jul 2019”
3.89 ha · Zoned RB · Rural Business
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Saint Margaret's Road, Dublin 11, Fingal
“commenced 01 Feb 2021, no completion certificate, planned end Jun 2022”
4.88 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Unit 633 Northwest Logistics Park, Kilshane Avenue, Northwest Business Park, Dublin, Fingal, D15 NXP6
“commenced 16 Jun 2022, no completion certificate, planned end Oct 2022”
0.91 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Building 5, IBM Technology Campus, Dublin, Fingal, D15 HN66
“commenced 11 Jun 2021, no completion certificate, planned end Aug 2021”
Zoned HT · High Technology
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Saint Margaret's Road, Dublin, Fingal, D11 X3W7
“commenced 09 Oct 2020, no completion certificate, planned end Nov 2021”
Zoned GE · General Employment
Stalled buildEndedRush-Lusk, Fingal
Naul Road, Ballyboughal, Dublin
“25 homes; commenced 16 Nov 2017, no completion certificate, planned end Jan 2018”
25 homes · Zoned OS · Open Space
Stalled buildEndedTallaght Central, South Dublin
Alexander House, Belgard Square North, Tallaght, D24, South Dublin, D24W8FP
“commenced 18 Feb 2022, no completion certificate, planned end Mar 2022”
1.56 ha · 43–125 homes · Zoned TC · To protect, improve and provide for the future development of Town…
Stalled buildEndedPalmerstown-Fonthill, South Dublin
Fonthill Road, Dublin, D22 E6N3
“commenced 14 Jun 2021, no completion certificate, planned end Jul 2021”
0.34 ha · Zoned MRC · To protect, improve and provide for the future development of a Major…
Stalled buildEndedPalmerstown-Fonthill, South Dublin
Unit 1, Liffey Valley Shopping Centre, Dublin 22, South Dublin, D22 E6N3
“commenced 03 Jul 2022, no completion certificate, planned end Nov 2022”
Zoned MRC · To protect, improve and provide for the future development of a Major…
Stalled buildEndedPalmerstown-Fonthill, South Dublin
“commenced 26 Jul 2021, no completion certificate, planned end Sep 2021”
0.34 ha · Zoned MRC · To protect, improve and provide for the future development of a Major…
Stalled buildEndedTallaght Central, South Dublin
Broomhill Road, Dublin, South Dublin, D24 F6PC
“commenced 12 Jul 2021, no completion certificate, planned end Aug 2021”
0.69 ha · 19–55 homes · Zoned REGEN · To facilitate enterprise and/or residential led regeneration
Stalled buildEndedClondalkin, South Dublin
Profile Park Business Park, New Nangor Road, Dublin 22, South Dublin
“commenced 04 Aug 2023, no completion certificate, planned end Apr 2025”
8.76 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
“commenced 13 Oct 2022, no completion certificate, planned end Feb 2023”
0.56 ha · Zoned RU · To protect and improve rural amenity and to provide for the…
Stalled buildEndedClondalkin, South Dublin
Garters Lane, Saggart, D24 KF8A
“commenced 28 Apr 2020, no completion certificate, planned end Apr 2020”
Zoned OS · To preserve and provide for open space and recreational amenities
Stalled buildEndedTallaght South, South Dublin
2020 Bianconi Avenue, Dublin, Dublin 24, D24 Y079
“commenced 21 Jun 2019, no completion certificate, planned end Aug 2019”
6.55 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedRathfarnham-Templeogue, South Dublin
Riversdale House, Butterfield Avenue,, Rathfarnham,, Dublin 14
“11 homes; commenced 30 Mar 2017, no completion certificate, planned end Jun 2017”
0.60 ha · 11 homes · Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedTallaght South, South Dublin
“commenced 18 Aug 2023, no completion certificate, planned end Sep 2023”
Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
Nangor Road, Clondalkin, South Dublin, D22 V8F8
“commenced 08 May 2023, no completion certificate, planned end Aug 2023”
35.7 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedRathfarnham-Templeogue, South Dublin
Riversdale House, Butterfield Avenue,, Rathfarnham, Dublin 14
“11 homes; commenced 25 Jul 2016, no completion certificate, planned end Oct 2016”
0.60 ha · 11 homes · Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedTallaght Central, South Dublin
Belgard Square West,, Dublin, D24 XFW2
“commenced 29 Jun 2021, no completion certificate, planned end Jan 2022”
0.85 ha · 23–67 homes · Zoned TC · To protect, improve and provide for the future development of Town…
Stalled buildEndedLucan, South Dublin
Unit 5, Adamstown Industrial Estate, Lucan, Co Dublin, South Dublin, K78 Y638
“commenced 17 Feb 2022, no completion certificate, planned end Apr 2022”
Zoned RU · To protect and improve rural amenity and to provide for the…
Stalled buildEndedPalmerstown-Fonthill, South Dublin
Fonthill Road, Dublin, South Dublin, D22 YD89
“commenced 01 Mar 2022, no completion certificate, planned end Jun 2022”
0.57 ha · Zoned RW · To provide for and consolidate retail warehousing
Stalled buildEndedTallaght South, South Dublin
Orchard Avenue, Dublin, Dublin 12, D24 RW52
“commenced 04 May 2018, no completion certificate, planned end Jun 2018”
Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedTallaght Central, South Dublin
Greenhills Road, Dublin, South Dublin, D24 HY58
“commenced 19 Jan 2023, no completion certificate, planned end Dec 2023”
Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedClondalkin, South Dublin
“commenced 31 May 2021, no completion certificate, planned end May 2022”
2.69 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedRathfarnham-Templeogue, South Dublin
Dargle Wood, Dublin, D16 FX45
“0 homes; commenced 26 Oct 2021, no completion certificate, planned end Dec 2021”
270 m² · Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedClondalkin, South Dublin
Profile Park Business Park, New Nangor Road, Dublin 22, South Dublin
“commenced 26 Jul 2023, no completion certificate, planned end Feb 2025”
8.76 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedTallaght South, South Dublin
Lake Drive, Dublin, Dublin 24, D24 N2HR
“commenced 09 Apr 2018, no completion certificate, planned end May 2018”
2.69 ha · Zoned EE · To provide for enterprise and employment related uses
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
claremount, Coolquoy Common, Fingal
“commenced 05 Aug 2020, no completion certificate, planned end Sep 2020”
0.96 ha · Zoned RU · Rural
Stalled buildEndedSwords, Fingal
Food Central, Roslin Food Park, Fingal, K67 V9F3
“commenced 31 Aug 2023, no completion certificate, planned end May 2024”
3.47 ha · Zoned FP · Food Park
Stalled buildEndedBalbriggan, Fingal
“commenced 10 Dec 2018, no completion certificate, planned end Apr 2019”
1.23 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Dublin, Dublin 15, D15 W244
“commenced 06 Dec 2019, no completion certificate, planned end Mar 2020”
2.73 ha · Zoned GE · General Employment
Stalled buildEndedSwords, Fingal
“commenced 15 Apr 2022, no completion certificate, planned end Jul 2022”
0.38 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Cedar Drive, Dublin Airport Logistics Park, Dublin, K67 YW68
“commenced 03 Nov 2022, no completion certificate, planned end Dec 2022”
2.37 ha · Zoned GE · General Employment
Stalled buildEndedRush-Lusk, Fingal
New Road, Donabate, Dublin
“1 homes; commenced 07 Jun 2019, no completion certificate, planned end Oct 2019”
5.17 ha · 1 home · Zoned RS · Residential
Stalled buildEndedHowth-Malahide, Fingal
43 Bayside Square West, Dublin, Fingal
“commenced 17 Aug 2021, no completion certificate, planned end Nov 2021”
0.99 ha · 27–79 homes · Zoned LC · Local Centre
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
2 Stemple Exchange, Blanchardstown Corporate Park, Ballycoolin, Dublin, Fingal, D15 E4FN
“commenced 14 Aug 2023, no completion certificate, planned end Nov 2023”
1.34 ha · Zoned HT · High Technology
Stalled buildEndedFingal
27 Northwood Avenue, Northwood, Dublin 9
“20 homes; commenced 14 Feb 2020, no completion certificate, planned end Jun 2020”
20 homes
Stalled buildEndedRush-Lusk, Fingal
Potrane Demense, Portrane Demesne, K36 X275
“commenced 07 May 2020, no completion certificate, planned end May 2020”
Zoned HA · High Amenity
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
634 Northwest Business Park, Dublin, Fingal, D15 RPYO
“commenced 25 Jan 2023, no completion certificate, planned end Sep 2023”
0.88 ha · Zoned GE · General Employment
Stalled buildEndedCastleknock, Fingal
6 Homeleigh, Dublin, D15 FHK4
“1 homes; commenced 27 Oct 2022, no completion certificate, planned end Mar 2023”
0.41 ha · 1 home · Zoned RS · Residential
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Unit 624, Northwest Business Park, Ballycoolin, Dublin 15, Dublin, Dublin 15, D15 ND71
“commenced 04 Jan 2019, no completion certificate, planned end Mar 2019”
2.71 ha · Zoned GE · General Employment
Stalled buildEndedBalbriggan, Fingal
Stephenstown Industrial Estate, Balbriggan, Dublin
“commenced 04 Oct 2018, no completion certificate, planned end Dec 2018”
0.51 ha · Zoned GE · General Employment
Stalled buildEndedFingal
Unnamed Road, Portrane Co Dublin, Fingal, K36 WR67
“commenced 14 Sep 2020, no completion certificate, planned end Dec 2020”
Stalled buildEndedCastleknock, Fingal
Grove Road, Dublin, Dublin 15, D15 W638
“commenced 11 Feb 2019, no completion certificate, planned end Apr 2019”
Zoned MC · Major Town Centre
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Saint Margaret's Road, Dublin 11, Fingal
“commenced 06 Apr 2021, no completion certificate, planned end Jul 2022”
4.88 ha · Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
“commenced 15 Nov 2020, no completion certificate, planned end Nov 2020”
20.3 ha · Zoned CI · Community Infrastructure
Stalled buildEndedRush-Lusk, Fingal
Biscuit Makers Factory, Ballyboughal, Dublin, A41 X903
“commenced 06 Aug 2018, no completion certificate, planned end Dec 2018”
0.52 ha · 14–41 homes · Zoned RV · Rural Village
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
Rosemount Park Drive, Dublin, Fingal, D11 W998
“commenced 02 Jun 2021, no completion certificate, planned end Aug 2021”
Zoned GE · General Employment
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
R135, Dunsoghly, Dublin 11
“commenced 28 Feb 2020, no completion certificate, planned end May 2020”
0.48 ha · Zoned GB · Green Belt
Stalled buildEndedBalbriggan, Fingal
Rathmooney, Lusk, Fingal
“commenced 26 Jan 2023, no completion certificate, planned end Feb 2023”
Zoned FP · Food Park
Stalled buildEndedBalbriggan, Fingal
L1285, Skerries, Dublin
“commenced 22 May 2020, no completion certificate, planned end Sep 2020”
1.76 ha · Zoned RU · Rural
Stalled buildEndedBlanchardstown-Mulhuddart, Fingal
17 North Park, Dublin, Fingal, D11 X253
“commenced 15 Feb 2021, no completion certificate, planned end Mar 2021”
Zoned GE · General Employment
Stalled buildEndedRush-Lusk, Fingal
Rear of Smyths Bridge House (Railway Lane), Donabate, Fingal
“1 homes; commenced 09 May 2023, no completion certificate, planned end Dec 2024”
2.14 ha · 1 home · Zoned RA · Residential Area
Stalled buildEndedBalbriggan, Fingal
Rathmooney, Lusk, Fingal, K45 NP03
“commenced 21 Feb 2022, no completion certificate, planned end Apr 2022”
0.46 ha · Zoned FP · Food Park
Stalled buildEndedCastleknock, Fingal
Grove Road, Blanchardstown, Dublin 15, D15 RK33
“97 homes; commenced 10 Apr 2018, no completion certificate, planned end Jun 2018”
0.34 ha · 97 homes · Zoned MC · Major Town Centre
Stalled buildEndedTallaght Central, South Dublin
at Tymon North, Community Nursing Home, Tallaght, Dublin 24., Dublin, South Dublin
“commenced 03 Dec 2020, no completion certificate, planned end Jan 2021”
Zoned RES · To protect and/or improve residential amenity
Stalled buildEndedRush-Lusk, Fingal
“6 homes; commenced 19 Jan 2022, no completion certificate, planned end Oct 2022”
0.26 ha · 6 homes · Zoned TC · Town and District Centre