Yesterday · 5 Permission running out 11 months left Naas, Co. Kildare
former Devoy Barracks , John Devoy Road , Naas
Permission for 219 homes granted 13 Oct 2022 runs out 12 Oct 2027, and building hasn't started.
An owner facing a lapse may sell, partner or extend.
4.16 ha · 219 homes · Zoned New Residential
Council selling land Blackrock, Dún Laoghaire-Rathdown
Dún Laoghaire-Rathdown Council gave notice it plans to sell or lease this land (12 Oct 2026).
“4.07. Proposed disposal of Council owned land at 169 Foxrock Close, Deansgrange, Dublin 18 - LD 2512”
Council land heading to a buyer or partner. Objections and offers go in now.
Council selling land Killiney-Shankill, Dún Laoghaire-Rathdown
Dún Laoghaire-Rathdown Council gave notice it plans to sell or lease this land (12 Oct 2026).
“4.06. Proposed disposal of a small area of Council owned land within Kilbogget Park, Cabinteely, Co. Dublin to ESB - LD2578”
Council selling land Glencullen-Sandyford, Dún Laoghaire-Rathdown
Dún Laoghaire-Rathdown Council gave notice it plans to sell or lease this land (12 Oct 2026).
“4.02. Proposed disposal of a small area of Council owned land along the Kilcross Road, Sandyford, Dublin 18 to ESB for the relocation and installation of a substation - LD2535”
Council selling land Dundrum, Dún Laoghaire-Rathdown
Dún Laoghaire-Rathdown Council gave notice it plans to sell or lease this land (12 Oct 2026).
“4.01. Proposed disposal of Council owned land at Saint Columbanus Road, Churchtown Lower, Dublin 14 to Gas Networks Ireland”
Zoned A · To provide residential development and improve residential amenity…
Sun 4 Oct · 1 Permission running out 11 months left Naas, Co. Kildare
Permission for 164 homes granted 5 Oct 2022 runs out 4 Oct 2027, and building hasn't started.
0.60 ha · 164 homes · Zoned New Residential
Wed 30 Sep · 1 Permitted, not started Mullingar, Co. Westmeath
Granted 30 Sept 2026 for 50 homes. No commencement notice yet; the permission runs to 30 Sept 2031.
Permitted but idle: the owner may want a builder or a buyer.
3.72 ha · 50 homes · Zoned Proposed Residential
Tue 29 Sep · 1 Permitted, not started Naas, Co. Kildare
Site at lands west of Naas Racecourse south of Dublin Road , north of Tipper Road and generally bounded by existing residential developments to the north south and west at Kings Court Kingsfurze Avenue The Woodlands and The Gallops , Kingsfurze
Granted 29 Sept 2026 for 213 homes. No commencement notice yet; the permission runs to 29 Sept 2031.
8.89 ha · 213 homes · Zoned New Residential
New development sites in Dublin, every Monday The week's new sites: permission running out, council selling land, derelict or stalled. Each with its source. Free while in beta.
Fri 25 Sep · 1 Permitted, not started Leixlip, Co. Kildare
Granted 25 Sept 2026 for 11 homes. No commencement notice yet; the permission runs to 25 Sept 2031.
0.29 ha · 11 homes · Zoned Existing Residential / Infill
Wed 23 Sep · 1 Permitted, not started Birr, Co. Offaly
Granted 23 Sept 2026 for 19 homes. No commencement notice yet; the permission runs to 23 Sept 2031.
0.80 ha · 19 homes · Zoned New Residential
Mon 21 Sep · 1 Permitted, not started Moate, Co. Westmeath
Granted 21 Sept 2026 for 46 homes. No commencement notice yet; the permission runs to 21 Sept 2031.
1.85 ha · 46 homes · Zoned Consolidation Site
Fri 18 Sep · 1 Permitted, not started Castlecomer, Co. Kilkenny
Granted 18 Sept 2026 for 14 homes. No commencement notice yet; the permission runs to 18 Sept 2031.
0.86 ha · 14 homes
Thu 17 Sep · 1 Permitted, not started Celbridge, Co. Kildare
Granted 17 Sept 2026 for 37 homes. No commencement notice yet; the permission runs to 17 Sept 2031.
2.72 ha · 37 homes
Wed 16 Sep · 1 Permission running out 11 months left Stillorgan, Dún Laoghaire-Rathdown
Permission for 12 homes granted 16 Sept 2022 runs out 16 Sept 2027, and building hasn't started.
0.50 ha · 12 homes
Tue 15 Sep · 1 Permission running out 11 months left Co. Kilkenny
Permission for 29 homes granted 16 Sept 2022 runs out 15 Sept 2027, and building hasn't started.
1.29 ha · 29 homes · Zoned New Residential
Mon 14 Sep · 2 Permitted, not started Glencullen-Sandyford, Dún Laoghaire-Rathdown
Granted 14 Sept 2026 for 23 homes. No commencement notice yet; the permission runs to 14 Sept 2031.
0.48 ha · 23 homes · Zoned A · To provide residential development and improve residential amenity…
Council selling land Balbriggan, Dún Laoghaire-Rathdown
Dún Laoghaire-Rathdown Council gave notice it plans to sell or lease this land (14 Sept 2026).
“4.02. Proposed Disposal of a 15-Year Lease of 17 Woodbrook Copse, Dublin Road, Bray, Co. Dublin, A98 W2T6 to Cheshire Ireland.”
Ended lately (103) Permissions that started, sites off a register, notices closed Sun 11 Oct Permission expired Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
0.4939ha site at nos. 60 (Cois Cnoc), 61, 62 & 63 (Innisfree), Stepaside Lane, Stepaside, Dublin 18
0.50 ha · 29 homes · Zoned NC · To protect, provide for and-or improve mixed-use neighbourhood centre…
Sun 27 Sep Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Frascati Road, Blackrock, Dublin, Dublin, Dún Laoghaire-Rathdown, A94 KX54
“commenced 14 Aug 2023, no completion certificate, planned end Oct 2023”
0.15 ha · 4–12 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
92 Bracken Road, Dublin, Dún Laoghaire-Rathdown, D18 CY92
“commenced 24 Jul 2023, no completion certificate, planned end Sep 2023”
0.42 ha · Zoned LIW · To improve and provide for low density warehousing-light industrial…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
77 Furze Road, Dublin, Dún Laoghaire-Rathdown, D18 C3X5
“commenced 10 May 2022, no completion certificate, planned end Dec 2022”
0.70 ha · Zoned LIW · To improve and provide for low density warehousing-light industrial…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
“commenced 22 Mar 2023, no completion certificate, planned end May 2023”
0.47 ha
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
3 Arkle Road, Dublin, Dún Laoghaire-Rathdown, D18 T6T7
“commenced 06 Mar 2023, no completion certificate, planned end May 2023”
0.68 ha · 18–54 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Pottery Road, Dublin, Dún Laoghaire-Rathdown, A96 F2A8
“commenced 25 Jan 2021, no completion certificate, planned end Jul 2021”
6.58 ha · Zoned E · To provide for economic development and employment
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Belfield Office Park, Beech Hill Rd,, Roebuck, Dublin 4, 8Q68 WH
“commenced 10 Dec 2018, no completion certificate, planned end Apr 2019”
0.28 ha · Zoned E · To provide for economic development and employment
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
MountainVIew, Central Park, Dublin, Dún Laoghaire-Rathdown, D18 XN97
“commenced 26 Jul 2022, no completion certificate, planned end Sep 2022”
6.87 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Ballymoss Road, Dublin, Dún Laoghaire-Rathdown, D18 Y2C9
“commenced 08 Mar 2022, no completion certificate, planned end Jun 2022”
0.38 ha · 10–30 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
“commenced 17 Dec 2021, no completion certificate, planned end Mar 2022”
Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
St. Patricks Boys' National School, Newgrange Rd, Blackrock, Dublin, Dublin, A94 FE02
“commenced 18 Jun 2020, no completion certificate, planned end Aug 2020”
2.68 ha · Zoned SNI · To protect, improve and encourage the provision of sustainable…
Stalled build Ended Dundrum, Dún Laoghaire-Rathdown
4 Dundrum Road, Dublin, Dún Laoghaire-Rathdown, D14 VX61
“commenced 15 Feb 2022, no completion certificate, planned end May 2022”
Zoned E · To provide for economic development and employment
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
CHERRYWOOD BUSINESS PARK, Dublin, South Dublin, D18 T3Y1
“commenced 26 Aug 2021, no completion certificate, planned end Dec 2021”
0.43 ha
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Dun Laoghaire Industrial Estate, Pottery Rd, Dun Laoghaire, Co Dublin, Dublin, Dún Laoghaire-Rathdown, A96 KW29
“commenced 23 Aug 2020, no completion certificate, planned end Jan 2021”
1.33 ha · Zoned E · To provide for economic development and employment
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
1 Pottery Road, Dublin, Monaghan, D18 X2H4
“commenced 11 Jan 2019, no completion certificate, planned end May 2019”
0.34 ha · Zoned E · To provide for economic development and employment
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Stillorgan Road, Dublin, Dún Laoghaire-Rathdown, D04 AE48
“commenced 12 Apr 2021, no completion certificate, planned end Jul 2022”
0.70 ha · 19–55 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Stillorgan Road, Dublin, Dún Laoghaire-Rathdown, D04 AE48
“commenced 26 Jan 2021, no completion certificate, planned end Jul 2021”
0.70 ha · 19–55 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
“commenced 10 Aug 2020, no completion certificate, planned end Dec 2020”
1.96 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Building 11, Cherrywood Business Park, Dublin, Dún Laoghaire-Rathdown, D18 DH50
“commenced 02 Dec 2020, no completion certificate, planned end May 2021”
0.51 ha
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
7 ST. HELEN'S VILLAS, ROCK ROAD, BOOTERSTOWN, CO. DUBLIN, Dublin, A94 H3F9
“1 homes; commenced 13 Sep 2018, no completion certificate, planned end Mar 2019”
600 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Blackthorn Road,, Dublin, D18 F5X2
“commenced 07 Aug 2019, no completion certificate, planned end Dec 2019”
0.79 ha · 22–63 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Mountain View, Central Park, Dublin, D18 XN97
“commenced 01 May 2019, no completion certificate, planned end Jul 2019”
6.87 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
BLACKTHORN ROAD, Dublin 18,SANDYFORD INDUSTRIAL ESTATE, D18 F5X2
“commenced 10 Apr 2019, no completion certificate, planned end Jul 2019”
0.79 ha · 22–63 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Barnhill Road, Dublin
“1 homes; commenced 03 Apr 2019, no completion certificate, planned end Oct 2019”
0.20 ha · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Cherrywood Park, Dublin, D18 DH50
“commenced 18 Mar 2019, no completion certificate, planned end Jun 2019”
0.51 ha
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
South County Business Park, Leopardstown, Dublin, Dublin, D18 DH6K
“commenced 23 Nov 2018, no completion certificate, planned end Dec 2019”
Zoned OE · To provide for office and enterprise development
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Ardagh Drive, Dublin, A94 EW97
“1 homes; commenced 19 Nov 2018, no completion certificate, planned end May 2019”
580 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Mountain View, Central Park, Dublin, D18XN97
“commenced 18 Jun 2018, no completion certificate, planned end Sep 2018”
6.87 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Corner of Carmanhal Road & Blackthorn Road, Dublin, NA
“commenced 24 Jul 2018, no completion certificate, planned end Sep 2018”
0.85 ha · 23–67 homes · Zoned A2 · To provide for the creation of sustainable residential neighbourhoods…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Arkle Road, Dublin, D18 Y3X2
“commenced 25 Apr 2018, no completion certificate, planned end Oct 2018”
0.41 ha · 11–32 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Block H, Central Park, Leopardstown, D18 CK74
“commenced 09 Nov 2018, no completion certificate, planned end Feb 2019”
0.54 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Blackthorn Road, Dublin, D18 KX32
“commenced 12 Apr 2018, no completion certificate, planned end Sep 2018”
80 m² · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
South Country Business Park, Dublin, D18 X5K7
“commenced 28 Apr 2018, no completion certificate, planned end Jul 2018”
Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Bracken Road, Dublin, D18 K2N9
“commenced 20 Oct 2018, no completion certificate, planned end Mar 2019”
0.35 ha · Zoned SNI · To protect, improve and encourage the provision of sustainable…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Sussex Street, Dublin, Dún Laoghaire-Rathdown, A96 C786
“10 homes; commenced 22 May 2023, no completion certificate, planned end Jun 2023”
520 m² · 10 homes · Zoned MTC · To protect, provide for and-or improve major town centre facilities
Stalled build Ended Dundrum, Dún Laoghaire-Rathdown
Sandyford Road, Dundrum Town Centre, Dún Laoghaire-Rathdown
“commenced 20 Dec 2022, no completion certificate, planned end Dec 2022”
0.49 ha · 13–39 homes · Zoned MTC · To protect, provide for and-or improve major town centre facilities
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
“1 homes; commenced 07 Jun 2022, no completion certificate, planned end Sep 2022”
630 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dundrum, Dún Laoghaire-Rathdown
RSA House, Sandyford Rd, Dublin, Dún Laoghaire-Rathdown, D16 FC92
“commenced 02 Dec 2021, no completion certificate, planned end Feb 2022”
3.13 ha · 87–249 homes · Zoned MTC · To protect, provide for and-or improve major town centre facilities
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Murphystown Way, Dublin 18, Dún Laoghaire-Rathdown, N/A
“commenced 16 Sep 2021, no completion certificate, planned end Feb 2022”
2.54 ha · 71–203 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Dublin, Dún Laoghaire-Rathdown, A94 H9T8
“commenced 25 Jun 2021, no completion certificate, planned end Feb 2023”
4.56 ha · 127–365 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Ballyogan Road, Leopardstown, Dublin 18
“commenced 19 May 2020, no completion certificate, planned end Aug 2020”
2.94 ha · 82–235 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Townlands of Laughanstown, Brennanstown & Cherrywood, Cherrywood, Dún Laoghaire-Rathdown, N/A
“commenced 21 May 2021, no completion certificate, planned end Sep 2021”
9.79 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Townlands of Laughanstown, Brennanstown & Cherrywood, Cherrywood, Dún Laoghaire-Rathdown, N/A
“commenced 21 May 2021, no completion certificate, planned end Sep 2021”
9.79 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Block H, Cherrywood Science & Technology Park,, Dublin, Dún Laoghaire-Rathdown, D18 W2P5
“commenced 12 May 2021, no completion certificate, planned end Aug 2021”
25.7 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Dublin, D18 TF72
“commenced 16 Jan 2019, no completion certificate, planned end Mar 2019”
0.65 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Tully Development Area 8, Barrington Road, Cherrywood, Dún Laoghaire-Rathdown, N/A
“commenced 14 Apr 2021, no completion certificate, planned end Oct 2021”
9.68 ha
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Rock Hill, Dublin, A94 W3F2
“commenced 15 Jul 2019, no completion certificate, planned end Oct 2019”
0.14 ha · 3–10 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Frascati Road, Dublin, Dún Laoghaire-Rathdown, A94 KX54
“commenced 31 Jul 2020, no completion certificate, planned end Aug 2020”
0.31 ha · 8–24 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
5 Leopardstown Rd, Dublin, Dún Laoghaire-Rathdown, D18 XN80
“commenced 19 Oct 2020, no completion certificate, planned end Aug 2021”
Zoned OE · To provide for office and enterprise development
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
“commenced 26 Mar 2020, no completion certificate, planned end Jan 2021”
4.28 ha
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
“1 homes; commenced 17 Dec 2019, no completion certificate, planned end Jul 2020”
640 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
28 Merville Avenue, Stillorgan, Dún Laoghaire-Rathdown, A94DK28
“1 homes; commenced 01 Feb 2021, no completion certificate, planned end May 2021”
520 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
18 Cherrywood, Loughlinstown
“commenced 15 Jul 2019, no completion certificate, planned end Aug 2019”
2.58 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Cherrywood Business Park, Building 4, Dublin, D18 K7W4
“commenced 26 Feb 2019, no completion certificate, planned end Apr 2019”
0.46 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
104 R116, Dublin, A96 T8X0
“0 homes; commenced 12 Nov 2018, no completion certificate, planned end Jan 2019”
440 m² · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Honeypark, Glenageary Road Upper & Kill Avenue, Dún Laoghaire
“197 homes; commenced 11 Aug 2015, no completion certificate, planned end Aug 2016”
410 m² · 197 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dundrum, Dún Laoghaire-Rathdown
Orwell Road, Dublin, Dún Laoghaire-Rathdown, D14 RX00
“1 homes; commenced 25 Aug 2022, no completion certificate, planned end Nov 2022”
480 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Kilmacud Road Upper, Stillorgan
“48 homes; commenced 04 Aug 2015, no completion certificate, planned end Aug 2017”
0.86 ha · 48 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
87 Stillorgan Road, Dublin, Dún Laoghaire-Rathdown, D14 W6X6
“commenced 09 Aug 2023, no completion certificate, planned end Sep 2023”
Zoned E · To provide for economic development and employment
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Vodafone, Dublin, Dún Laoghaire-Rathdown, D18 XN97
“commenced 31 Jul 2023, no completion certificate, planned end Aug 2023”
Zoned OE · To provide for office and enterprise development
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
9 The Hill, Dublin, a94 a240
“commenced 11 Mar 2019, no completion certificate, planned end Sep 2019”
1.33 ha · 37–106 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
4 Blackthorn Road, Dublin, D18 F5X2
“commenced 02 Jul 2019, no completion certificate, planned end Sep 2019”
0.42 ha · 11–33 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Carysfort Avenue, Blackrock, Dún Laoghaire-Rathdown, A94 H2X4
“commenced 21 Jun 2022, no completion certificate, planned end Oct 2022”
Zoned E · To provide for economic development and employment
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
L5, Termini Building, 3 Arkle Road, Sandyford, Dublin 18, Dún Laoghaire-Rathdown, D18 T6T7
“commenced 02 Nov 2021, no completion certificate, planned end Dec 2021”
0.68 ha · 18–54 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Central Park, Leopardstown, Dublin, Dún Laoghaire-Rathdown, D18 NH10
“commenced 30 Aug 2021, no completion certificate, planned end Mar 2022”
6.87 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
89 Furze Road, Dublin, D18 CK84
“commenced 24 Aug 2021, no completion certificate, planned end Jan 2022”
0.15 ha · Zoned LIW · To improve and provide for low density warehousing-light industrial…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Block C Central Park Leopardstown, Dublin, D18 N924
“commenced 29 Jun 2018, no completion certificate, planned end Sep 2018”
6.87 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Central Park, Leopardstown, Dublin, D18 X9R6
“commenced 21 Feb 2019, no completion certificate, planned end Mar 2019”
6.87 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Dublin, Dún Laoghaire-Rathdown, D18 C9C5
“commenced 27 Aug 2021, no completion certificate, planned end Dec 2021”
0.68 ha · 18–54 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Murphystown Way, dublin 18, Dún Laoghaire-Rathdown, 0000
“commenced 27 Jul 2020, no completion certificate, planned end Oct 2020”
9.63 ha · 269–770 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Dublin, D14 FH90
“commenced 07 Jul 2020, no completion certificate, planned end Nov 2020”
Zoned E · To provide for economic development and employment
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Brewery Road, Stillorgan, Blackrock, Dublin, A94 W0PP
“commenced 23 Jan 2020, no completion certificate, planned end Apr 2020”
1.80 ha · 50–144 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
31 Trimleston Avenue, Booterstown, A94 TX94
“commenced 25 Nov 2019, no completion certificate, planned end Jan 2020”
0.55 ha · 15–43 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Park Court, Glenageary, A96 N6X3
“commenced 26 Aug 2019, no completion certificate, planned end Sep 2019”
0.40 ha · 11–32 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
Stradbrook Road, Dublin, A94 K2V8
“commenced 10 Sep 2019, no completion certificate, planned end Nov 2019”
5.01 ha · Zoned F · To preserve and provide for open space with ancillary active…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Arkle Road, Sandyford, D18 X6N2
“commenced 04 Mar 2019, no completion certificate, planned end May 2019”
590 m² · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
8 Pottery Road, Dublin, A96 W6T8
“commenced 01 Jun 2018, no completion certificate, planned end Sep 2018”
10.5 ha · Zoned E · To provide for economic development and employment
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
“commenced 09 Apr 2018, no completion certificate, planned end Jul 2018”
0.79 ha · 22–63 homes · Zoned MOC · To provide for a mix of uses. Which complements the inner core, but…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Stanford Park, Foxrock, Dublin 18
“16 homes; commenced 13 Oct 2017, no completion certificate, planned end Jan 2019”
1.16 ha · 16 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
Frascati Road, Blackrock, Dublin, Dún Laoghaire-Rathdown, A94 X9Y3
“commenced 31 Jul 2020, no completion certificate, planned end Aug 2020”
0.30 ha · 8–24 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
“commenced 17 Jul 2020, no completion certificate, planned end Sep 2020”
1.36 ha · 38–108 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
“commenced 17 Jun 2019, no completion certificate, planned end Sep 2019”
1.46 ha
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Laughanstown, Cherrywood, Dublin 18, Dún Laoghaire-Rathdown
“1 homes; commenced 14 Feb 2022, no completion certificate, planned end Jun 2022”
9.79 ha · 1 home
Stalled build Ended Dundrum, Dún Laoghaire-Rathdown
“commenced 18 May 2021, no completion certificate, planned end Jul 2021”
630 m² · Zoned MTC · To protect, provide for and-or improve major town centre facilities
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Block H, Cherrywood Science & Technology Park,, Dublin, Dún Laoghaire-Rathdown, D18 W2P5
“commenced 12 Apr 2021, no completion certificate, planned end Jul 2021”
25.7 ha
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
“commenced 08 Apr 2021, no completion certificate, planned end Jul 2021”
1.29 ha · 36–103 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Blackrock, Dún Laoghaire-Rathdown
3 Frascati Road, Blackrock, 1400
“commenced 11 Feb 2020, no completion certificate, planned end Jun 2020”
0.11 ha · 3–8 homes · Zoned DC · To protect, provide for and-or improve mixed-use district centre…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Land at Cherrywood, Dublin, Dún Laoghaire-Rathdown, D18 WD60
“1 homes; commenced 08 Feb 2021, no completion certificate, planned end Jun 2021”
17.0 ha · 1 home
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Brewery Road, Dublin, Dún Laoghaire-Rathdown
“commenced 12 Oct 2020, no completion certificate, planned end Aug 2021”
21.4 ha · Zoned F · To preserve and provide for open space with ancillary active…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
“commenced 25 Aug 2020, no completion certificate, planned end Sep 2020”
0.35 ha · Zoned OE · To provide for office and enterprise development
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
York rd., Dublin, Dún Laoghaire-Rathdown, A96 H361
“1 homes; commenced 02 Sep 2020, no completion certificate, planned end Oct 2020”
600 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Murphystown Way, Dublin, Dún Laoghaire-Rathdown, 0000
“commenced 13 Aug 2020, no completion certificate, planned end Dec 2020”
9.63 ha · 269–770 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dundrum, Dún Laoghaire-Rathdown
100 Marlay Court, Dublin, D14 VA44
“1 homes; commenced 22 Jun 2020, no completion certificate, planned end Sep 2020”
270 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
Land at Cherrywood, Dublin 18, D18 WD60
“1 homes; commenced 20 May 2020, no completion certificate, planned end Aug 2020”
17.0 ha · 1 home
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Mount Anville Road, Dublin 14, D14 H5P8
“93 homes; commenced 14 Nov 2019, no completion certificate, planned end Feb 2020”
2.75 ha · 93 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
Murphystown Way, Dublin, 0000
“commenced 29 Aug 2019, no completion certificate, planned end May 2020”
9.63 ha · 269–770 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Dún Laoghaire, Dún Laoghaire-Rathdown
21 Johnstown Road, Cabinteely
“49 homes; commenced 14 Jun 2019, no completion certificate, planned end Sep 2019”
0.29 ha · 49 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Brennanstown Road, Cabinteely, n/a
“commenced 16 Apr 2019, no completion certificate, planned end Aug 2019”
3.67 ha · 102–293 homes · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Stillorgan, Dún Laoghaire-Rathdown
Deerpark Road, Mount Merrion,, Blackrock, A94 YX95
“commenced 06 Feb 2019, no completion certificate, planned end Apr 2019”
0.34 ha · 9–27 homes · Zoned NC · To protect, provide for and-or improve mixed-use neighbourhood centre…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
18 Cherrywood, Dublin, A96 Y4E9
“commenced 19 Dec 2018, no completion certificate, planned end Feb 2019”
300 m² · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Killiney-Shankill, Dún Laoghaire-Rathdown
18 Cherrywood, Loughlinstown
“1 homes; commenced 12 Nov 2018, no completion certificate, planned end Jan 2019”
300 m² · 1 home · Zoned A · To provide residential development and improve residential amenity…
Stalled build Ended Glencullen-Sandyford, Dún Laoghaire-Rathdown
88 Furze Road, Sandyford, Dublin, D18 EK00
“commenced 24 Jun 2019, no completion certificate, planned end Dec 2019”
0.15 ha · Zoned LIW · To improve and provide for low density warehousing-light industrial…